Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMP Topic 3 Question 64 Discussion

Actual exam question for PMI's Project Management Professional (2024) exam
Question #: 64
Topic #: 3
[All Project Management Professional (2024) Questions]

A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be

required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.

What should project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel