Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Leatha
6 months agoLouvenia
6 months agoMohammad
7 months agoRosendo
7 months agoAlethea
7 months agoFairy
7 months agoVirgie
8 months agoTwana
8 months agoErasmo
8 months agoKatina
8 months agoNaomi
8 months agoLakeesha
8 months agoTheola
8 months agoAnisha
8 months agoJunita
8 months agoRikki
8 months agoElina
8 months agoAmina
1 year agoShalon
11 months agoJulian
11 months agoGerald
11 months agoCassi
11 months agoLisha
1 year agoJesusa
11 months agoAvery
11 months agoBlondell
11 months agoLinn
12 months agoSherita
12 months agoCathern
12 months agoElise
1 year agoJestine
1 year agoElly
1 year agoTrina
1 year agoTresa
12 months agoGianna
12 months agoLavonna
12 months agoEva
12 months agoGracia
12 months agoShawnee
12 months agoAdell
12 months agoAnnabelle
1 year agoTamesha
1 year agoJoanne
1 year agoNada
1 year agoAndree
1 year agoPedro
1 year agoLaticia
1 year agoJuliana
1 year agoCarmelina
1 year agoJimmie
1 year ago