Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 78 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 78
Topic #: 8
[All PMI-SP Questions]

Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Amina
7 days ago
A weekly status report? Sounds like the customers want to micromanage this project! But I guess A is the right answer here.
upvoted 0 times
...
Lisha
14 days ago
Hmm, the communications management plan makes the most sense to me. It's all about managing project information, so that's where I'd put it.
upvoted 0 times
Elly
9 days ago
A) Communications management plan
upvoted 0 times
...
...
Trina
28 days ago
Weekly reports? That's a lot of paperwork! But I guess it's better to keep the customers in the loop. I'd go with A on this one.
upvoted 0 times
Tamesha
3 days ago
That sounds like the right place to document it.
upvoted 0 times
...
Joanne
16 days ago
A) Communications management plan
upvoted 0 times
...
...
Nada
1 months ago
I think Steve could also document this in the Schedule management plan, as it relates to the frequency of project information updates.
upvoted 0 times
...
Andree
1 months ago
A weekly status report sounds like a great idea! The communications management plan seems like the perfect place to document this.
upvoted 0 times
Pedro
5 days ago
B) Issues log
upvoted 0 times
...
Laticia
6 days ago
That's right, the communications management plan is where Steve should document this information.
upvoted 0 times
...
Juliana
10 days ago
A) Communications management plan
upvoted 0 times
...
...
Carmelina
1 months ago
I agree with Jimmie. The Communications management plan is where all communication-related information should be documented.
upvoted 0 times
...
Jimmie
1 months ago
I think Steve should document this information in the Communications management plan.
upvoted 0 times
...

Save Cancel