Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Leatha
5 months agoLouvenia
5 months agoMohammad
5 months agoRosendo
5 months agoAlethea
6 months agoFairy
6 months agoVirgie
6 months agoTwana
6 months agoErasmo
6 months agoKatina
6 months agoNaomi
6 months agoLakeesha
6 months agoTheola
7 months agoAnisha
7 months agoJunita
7 months agoRikki
7 months agoElina
7 months agoAmina
11 months agoShalon
9 months agoJulian
9 months agoGerald
9 months agoCassi
10 months agoLisha
11 months agoJesusa
10 months agoAvery
10 months agoBlondell
10 months agoLinn
10 months agoSherita
10 months agoCathern
10 months agoElise
11 months agoJestine
11 months agoElly
11 months agoTrina
12 months agoTresa
10 months agoGianna
10 months agoLavonna
10 months agoEva
10 months agoGracia
10 months agoShawnee
10 months agoAdell
10 months agoAnnabelle
11 months agoTamesha
11 months agoJoanne
11 months agoNada
1 year agoAndree
1 year agoPedro
11 months agoLaticia
11 months agoJuliana
11 months agoCarmelina
1 year agoJimmie
1 year ago