Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Leatha
3 months agoLouvenia
3 months agoMohammad
3 months agoRosendo
4 months agoAlethea
4 months agoFairy
4 months agoVirgie
4 months agoTwana
4 months agoErasmo
5 months agoKatina
5 months agoNaomi
5 months agoLakeesha
5 months agoTheola
5 months agoAnisha
5 months agoJunita
5 months agoRikki
5 months agoElina
5 months agoAmina
9 months agoShalon
7 months agoJulian
8 months agoGerald
8 months agoCassi
8 months agoLisha
10 months agoJesusa
8 months agoAvery
8 months agoBlondell
8 months agoLinn
8 months agoSherita
8 months agoCathern
8 months agoElise
9 months agoJestine
9 months agoElly
9 months agoTrina
10 months agoTresa
8 months agoGianna
8 months agoLavonna
8 months agoEva
8 months agoGracia
8 months agoShawnee
8 months agoAdell
9 months agoAnnabelle
9 months agoTamesha
9 months agoJoanne
10 months agoNada
10 months agoAndree
10 months agoPedro
9 months agoLaticia
9 months agoJuliana
9 months agoCarmelina
10 months agoJimmie
10 months ago