Steve is the project manager for the POK Project. He is working with the project customers to determine how frequently they'd like to receive the project information. The customers would like weekly status reports on how the project is performing. Where should Steve document this information?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Leatha
8 months agoLouvenia
8 months agoMohammad
8 months agoRosendo
9 months agoAlethea
9 months agoFairy
9 months agoVirgie
9 months agoTwana
9 months agoErasmo
10 months agoKatina
10 months agoNaomi
10 months agoLakeesha
10 months agoTheola
10 months agoAnisha
10 months agoJunita
10 months agoRikki
10 months agoElina
10 months agoAmina
1 year agoShalon
1 year agoJulian
1 year agoGerald
1 year agoCassi
1 year agoLisha
1 year agoJesusa
1 year agoAvery
1 year agoBlondell
1 year agoLinn
1 year agoSherita
1 year agoCathern
1 year agoElise
1 year agoJestine
1 year agoElly
1 year agoTrina
1 year agoTresa
1 year agoGianna
1 year agoLavonna
1 year agoEva
1 year agoGracia
1 year agoShawnee
1 year agoAdell
1 year agoAnnabelle
1 year agoTamesha
1 year agoJoanne
1 year agoNada
1 year agoAndree
1 year agoPedro
1 year agoLaticia
1 year agoJuliana
1 year agoCarmelina
1 year agoJimmie
1 year ago