What is the formula to find the schedule performance index?
The schedule performance index shows how well the project is performing on schedule.
It is found by dividing the earned value by the
planned value.
Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that
the schedule is ahead or behind what
was planned for this period in time. The schedule variance is calculated based on the following
formula:
SV = Earned Value (EV) - Planned Value (PV)
If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater
than 0 shows that the project is ahead of
the planned schedule. A value of 0 indicates that the project is right on target.
Answer option D is incorrect. EV-AC is the project's cost variance.
Answer option B is incorrect. EV/AC is the project's cost performance index.
Answer option A is incorrect. EV-PV is the project's schedule variance.
Raina
10 months agoIvan
11 months agoHoward
11 months agoMagnolia
11 months agoCory
11 months agoYuki
11 months agoElenora
11 months agoKerry
11 months agoMaynard
11 months agoSherly
12 months agoDemetra
12 months agoAnnice
12 months ago