You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some doubts about the inputs of the Identify Stakeholder process. What is referred to as an input to the identify stakeholder process in project communication management?
The project charter is an input to the identify stakeholder process. It provides information about the
internal and external parties concerned
and is affected by the project.
The project charter is the document that formally authorizes a project. The project charter provides
the project manager with the authority to
apply organizational resources to project activities. According to PMBOK Guide, the project charter
should address the following information:
Requirements that satisfy customer, sponsor, and other stakeholder needs, wants and expectations
Business needs, high-level project description, or product requirements that the project is
undertaken to address
Project purpose or justification
Assigned Project Manager and authority level
Summary milestone schedule
Stakeholder influences
Functional organizations and their participation
Organizational, environmental and external assumptions
Organizational, environmental and external constraints
Business case justifying the project, including return on investment
Summary budget
If required, it also authorizes the next project phase, and updates the charter. The project manager
should always be assigned prior to the
start of planning, and preferably while the project charter is being developed.
Answer option A is incorrect. Expert judgment is a technique based on a set of criteria that has been
acquired in a specific knowledge area or
product area. It is obtained when the project manager or project team requires specialized
knowledge that they do not possess. Expert
judgment involves people most familiar with the work of creating estimates. Preferably, the project
team member who will be doing the task
should complete the estimates. Expert judgment is applied when performing administrative closure
activities, and experts should ensure the
project or phase closure is performed to the appropriate standards.
Answer option C is incorrect. Stakeholder analysis is the identification of stakeholder needs, wants
and expectations. It involves the
documentation, prioritization, and quantification of the needs to help define the project scope.
Stakeholders' interests may be positively or
negatively affected by execution or completion of the project and they may also exert influence over
the project and its deliverables.
Answer option D is incorrect. The stakeholder register is a project management document that
contains a list of the stakeholders associated
with the project. It assesses how they are involved in the project and identifies what role they play in
the organization. The information in this
document can be very perceptive and is meant for limited exchange only. It also contains relevant
information about the stakeholders, such as
their requirements, expectations, and influence on the project.