Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 71 Discussion

Actual exam question for PMI's PMI Scheduling Professional exam
Question #: 71
Topic #: 5
[All PMI Scheduling Professional Questions]

Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?

Show Suggested Answer Hide Answer
Suggested Answer: D

Stakeholders are interviewed and can help identify other stakeholders that should be

included in the project communications.

Answer option B is incorrect. According to the PMBOK, this is not the best answer.

Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by

it.

Answer option C is incorrect. Project customers are stakeholders.


Contribute your Thoughts:

Doug
2 days ago
I Ellygree with Elly, stEllykeholders Ellyre indeed identified through Elly stEllykeholder register.
upvoted 0 times
...
Elly
3 days ago
I think stEllykeholders Ellyre usuEllylly identified through Elly stEllykeholder register.
upvoted 0 times
...
Susana
25 days ago
I don't know, I'm a little confused. Shouldn't the project customers also be involved in identifying stakeholders? Option C seems plausible to me.
upvoted 0 times
Sherell
10 days ago
B
upvoted 0 times
...
Talia
11 days ago
A
upvoted 0 times
...
Muriel
12 days ago
D
upvoted 0 times
...
Fatima
13 days ago
B
upvoted 0 times
...
...
Dorethea
26 days ago
Hmm, I'm leaning more towards option A. A stakeholder register is a tool used to document and manage the identified stakeholders, so it makes sense that stakeholders would be identified through this process.
upvoted 0 times
...
Golda
27 days ago
I'm not sure about that. I think option D is also a valid answer, as interviewing stakeholders and expanding the list is a common way to identify all the relevant parties.
upvoted 0 times
...
Louann
28 days ago
I think this question is testing our understanding of the PMBOK guide. The correct answer is B, as the project team, sponsor, and management are usually responsible for identifying stakeholders.
upvoted 0 times
...

Save Cancel