When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.
What should the project manager do?
Erick
1 months agoJavier
2 days agoHaydee
7 days agoAide
10 days agoNaomi
18 days agoBrendan
1 months agoDelfina
1 months agoDesmond
1 months agoLeslie
2 months agoRessie
13 days agoAlpha
28 days agoFausto
2 months agoMelita
2 months ago