Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 89 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 89
Topic #: 8
[All PMI-RMP Questions]

Members of a project team are not taking their risk management responsibilities seriously. They do not consider risk management as primary to the project's success and do not believe that the benefits are significant.

What should the risk manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Gilma
12 days ago
Risk management? More like risk mana-goo-ment, am I right? Seriously though, B sounds like the way to go - gotta get those team members pumped up!
upvoted 0 times
...
Nelida
13 days ago
Personally, I'd go with D. Ensuring consistent risk language will help the team communicate better and take it more seriously.
upvoted 0 times
...
Kimbery
18 days ago
Hmm, I'm not sure. Maybe A would be a good option to review the risk thresholds and get the team on the same page.
upvoted 0 times
Sharita
1 days ago
A) Schedule a meeting to review and develop realistic risk thresholds with the project team.
upvoted 0 times
...
...
Gerald
23 days ago
I disagree, I think C is the best answer. The risk management responsibilities need to be clearly defined in the plan for the team to understand their role.
upvoted 0 times
...
Dan
25 days ago
I think the answer is B. Motivating the team and getting them engaged in risk management activities is key to getting them to take it seriously.
upvoted 0 times
...
Chara
1 months ago
I believe motivating and influencing the project team with risk engagement activities like workshops could also help in making them understand the significance of risk management.
upvoted 0 times
...
Keva
2 months ago
I agree with Thersa. It's important to set clear expectations and guidelines for managing risks in the project.
upvoted 0 times
...
Thersa
2 months ago
I think the risk manager should schedule a meeting to review and develop realistic risk thresholds with the project team.
upvoted 0 times
...

Save Cancel