Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 6 Question 104 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 104
Topic #: 6
[All PMI-RMP Questions]

A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.

What should the project manager do next to avoid similar risks?

Show Suggested Answer Hide Answer
Suggested Answer: B

The project manager should reassess risks by conducting a new assumptions and constraints analysis. This will help identify any previously overlooked risks and ensure that the risk register is comprehensive and up-to-date.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel