A risk manager has to Inform a project sponsor of the expected duration of an entire project. The project has three main tasks, each with different probabilities of duration. Which analytical tool should the risk manager use?
Monte Carlo simulation is definitely the way to go here. It's the only tool that can handle the different probabilities and durations of the project tasks.
Xenia
17 days agoKarl
20 days agoRomana
4 days agoRebeca
25 days agoShenika
7 days agoJina
1 months agoKristeen
18 days agoCristy
1 months agoFrancis
1 months agoAnnmarie
1 months agoJordan
2 months ago