Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 4 Question 66 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 66
Topic #: 4
[All PMI-RMP Questions]

During project execution tor a software development program a risk manager notices the results vary from the stated expectations in the planning phase. The project team states that there was unrealistic planning.

What should the risk manager do next to understand the differences between planning and execution?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Shakira
11 days ago
I bet the project team is just making excuses because they spent the entire budget on a fancy team-building retreat at a luxury resort. The risk manager should probably just follow the money trail.
upvoted 0 times
...
Rosendo
12 days ago
Engaging with the team is the way to go. They're the ones who can provide the insights on what went wrong. Plus, it's always fun to see them squirm when the risk manager starts asking tough questions.
upvoted 0 times
...
Tracie
30 days ago
Prepare a management of change (MOC) to adjust the project cost and duration? That's like trying to put a bandaid on a broken leg. We need to dig deeper and find the real problem!
upvoted 0 times
Wilda
19 days ago
A) Move forward with the lessons learned from the sprint.
upvoted 0 times
...
...
Dorothy
1 months ago
Presenting the actual results to the sponsor is a great idea. They need to be informed of the discrepancies between planning and execution.
upvoted 0 times
...
Skye
1 months ago
The risk manager should definitely review the assumptions to understand any changes that occurred. Lessons learned from the sprint are good, but getting to the root of the issue is crucial.
upvoted 0 times
Lamonica
4 days ago
D) Engage with the team to present the actual results to the sponsor.
upvoted 0 times
...
Shawna
7 days ago
B) Review the assumptions to understand any change.
upvoted 0 times
...
Phyliss
10 days ago
D) Engage with the team to present the actual results to the sponsor.
upvoted 0 times
...
Justine
11 days ago
B) Review the assumptions to understand any change.
upvoted 0 times
...
...
Melvin
1 months ago
I think preparing a management of change (MOC) to adjust the project cost and duration could also be helpful in this situation.
upvoted 0 times
...
Valda
1 months ago
I agree with Malcom. It's important to identify where the planning went wrong.
upvoted 0 times
...
Malcom
2 months ago
I think the risk manager should review the assumptions to understand any change.
upvoted 0 times
...

Save Cancel