Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 2 Question 77 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 77
Topic #: 2
[All PMI-RMP Questions]

A budget change request was initiated by a functional manager in an organization due to a shortage in the functional manager's department budget. The functional manager asks the CEO to approve utilization of a contingency budget reserved for one of the projects in its closing phase.

What should the risk manager of the related project have done to prevent this situation from happening?

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

Contribute your Thoughts:

Rosio
5 days ago
I bet the risk manager was too busy playing Tetris to properly monitor the project's budget. That's the real reason this situation happened.
upvoted 0 times
...
Ammie
6 days ago
Haha, the risk manager should have consulted a crystal ball to predict the future budget needs. That would have been more effective than any of these options!
upvoted 0 times
...
Mattie
17 days ago
Communicating better with the CEO? Really? I doubt that would have made a difference. The risk manager should have been on top of the project's finances and not let it get to this point.
upvoted 0 times
Sylvie
3 days ago
A: The risk manager should have reformed the risk monitoring and closing process properly.
upvoted 0 times
...
...
Silvana
18 days ago
Educating the project team on budget change requests is a good idea, but I don't think it would have solved the root cause of the problem. The risk manager needs to be proactive in managing the project's budget.
upvoted 0 times
...
Lashandra
27 days ago
Creating the project work plan and budget more accurately seems like the best option here. If the budget was planned properly, there wouldn't have been a shortage in the first place.
upvoted 0 times
Linsey
8 days ago
User 1: The risk manager should have created the project work plan and budget more accurately.
upvoted 0 times
...
...
Dominga
1 months ago
Maybe educating the project team on budget change requests could have also helped in this situation.
upvoted 0 times
...
Wenona
1 months ago
I think the risk manager should have reformed the risk monitoring and closing process properly. Having a robust process in place could have helped prevent this situation.
upvoted 0 times
Albina
1 days ago
B) Created the project work plan and budget more accurately.
upvoted 0 times
...
Nobuko
3 days ago
A) Reformed the risk monitoring and closing process properly.
upvoted 0 times
...
...
Marg
1 months ago
I agree with Colby, better risk management could have prevented this budget shortage.
upvoted 0 times
...
Colby
2 months ago
The risk manager should have reformed the risk monitoring and closing process properly.
upvoted 0 times
...

Save Cancel