Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI PgMP Exam - Topic 3 Question 120 Discussion

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?
D) -$117,295
A) -$85,230
B) $821,065
C) -$284,100

PMI PgMP Exam - Topic 3 Question 120 Discussion

Actual exam question for PMI's PgMP exam
Question #: 120
Topic #: 3
[All PgMP Questions]

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent

$789,000. The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule. Based on this information, what is the schedule variance (SV) of this program?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Maryann
2 days ago
If I recall correctly, the planned value should be based on the budget at completion and the percentage of completion. So, I guess we need to calculate that first?
upvoted 0 times
...
Carylon
7 days ago
I think I remember that schedule variance is calculated by subtracting the planned value from the earned value. But I'm not entirely sure how to find those values here.
upvoted 0 times
...

Save Cancel