Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PgMP Topic 2 Question 74 Discussion

Actual exam question for PMI's PgMP exam
Question #: 74
Topic #: 2
[All PgMP Questions]

A request for proposal (RFP) yields a bid with a better delivery schedule and a lower cost, but originates from a vendor not on the prequalified vendor list. During the final review of the RFPs, the program manager is informed that the new bidder is a relative of the project manager. Although the bid meets all company policies, the program manager is concerned about a conflict of interest.

What should the program manager do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Hassie
2 days ago
Oh, the joys of project management! This is like a real-life episode of 'Nepotism Negotiation Nightmare'. Option C, please!
upvoted 0 times
...
Nana
3 days ago
Conflict of interest? Yikes! This is like an episode of 'Project Management Gone Wild'. Option C all the way, baby!
upvoted 0 times
...
Stephania
6 days ago
Oof, tough call. The new vendor seems like the better option, but the conflict of interest is a major red flag. Better play it safe and pick C.
upvoted 0 times
...
Margurite
11 days ago
Hmm, better delivery schedule and lower cost? Sounds like a no-brainer. But with that family connection, gotta go with C. Transparency is key.
upvoted 0 times
...
Rolande
12 days ago
Wait, a family member of the project manager is bidding? That's sketchy! Better go with option C and let the sponsor know what's up.
upvoted 0 times
...
Kallie
2 months ago
I think the program manager should advise the sponsor of a possible conflict of interest before awarding the bid. Transparency is key in these situations.
upvoted 0 times
...
Marjory
2 months ago
I agree with Lawrence. It's important to follow company policies and avoid any potential conflicts of interest.
upvoted 0 times
...
Lawrence
2 months ago
I think the program manager should select the best bid from the prequalified vendor list.
upvoted 0 times
...

Save Cancel