Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

NCMA Exam CPCM Topic 6 Question 92 Discussion

Actual exam question for NCMA's CPCM exam
Question #: 92
Topic #: 6
[All CPCM Questions]

Liquidated damages are a negative incentive (penalty) for:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Kaycee
2 months ago
As a project manager, I live in fear of liquidated damages. Gotta make sure we deliver on time, no matter what!
upvoted 0 times
...
Lorita
2 months ago
Haha, I was tempted to go with D) Requirements gap, just to be that guy who picks the weird answer. But B) Late delivery is the correct choice here.
upvoted 0 times
Cecil
6 days ago
Late delivery is definitely a common reason for liquidated damages in contracts.
upvoted 0 times
...
Hyun
7 days ago
It's always better to play it safe and go with the obvious answer.
upvoted 0 times
...
Silvana
8 days ago
Yeah, picking D) Requirements gap would have been a risky move.
upvoted 0 times
...
Angella
30 days ago
I agree, B) Late delivery is the correct choice for liquidated damages.
upvoted 0 times
...
...
Candra
2 months ago
Hmm, I was stuck between B) Late delivery and C) Do not achieve requirements. But B) is the more direct penalty for not meeting the project timeline.
upvoted 0 times
Dorothy
29 days ago
Liquidated damages are definitely a way to ensure project deadlines are met.
upvoted 0 times
...
Tamekia
2 months ago
Yeah, C) Do not achieve requirements is more about not meeting the project specifications.
upvoted 0 times
...
Lourdes
2 months ago
I agree, B) Late delivery is a more direct penalty for not meeting the project timeline.
upvoted 0 times
...
...
Slyvia
2 months ago
I was going to say A) Over budget, but that doesn't quite fit the description of a 'negative incentive'. B) Late delivery makes more sense.
upvoted 0 times
Lindy
1 months ago
Yes, it's a way to ensure that projects are completed on time.
upvoted 0 times
...
Lelia
1 months ago
I agree, liquidated damages are a penalty for not meeting the delivery timeline.
upvoted 0 times
...
Geoffrey
2 months ago
Late delivery makes more sense.
upvoted 0 times
...
...
Margret
3 months ago
B) Late delivery seems like the obvious answer here. Liquidated damages are a way to incentivize on-time project completion.
upvoted 0 times
Elbert
1 months ago
B) Late delivery and not achieving requirements are both valid reasons for liquidated damages.
upvoted 0 times
...
Pamella
1 months ago
C) Do not achieve requirements could also be a reason for liquidated damages. Meeting all project requirements is crucial.
upvoted 0 times
...
Rosina
1 months ago
A) Over budget is also a possibility. It's important to stay within budget to avoid penalties.
upvoted 0 times
...
Sunshine
2 months ago
B) Late delivery seems like the obvious answer here. Liquidated damages are a way to incentivize on-time project completion.
upvoted 0 times
...
...
Ashley
3 months ago
I believe it's important to have liquidated damages to ensure timely delivery.
upvoted 0 times
...
Vanda
3 months ago
I agree with Eleni, it's a penalty for not meeting the deadline.
upvoted 0 times
...
Eleni
3 months ago
I think liquidated damages are for late delivery.
upvoted 0 times
...

Save Cancel