Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

NCMA Exam CPCM Topic 6 Question 92 Discussion

Actual exam question for NCMA's CPCM exam
Question #: 92
Topic #: 6
[All CPCM Questions]

Liquidated damages are a negative incentive (penalty) for:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Kaycee
12 days ago
As a project manager, I live in fear of liquidated damages. Gotta make sure we deliver on time, no matter what!
upvoted 0 times
...
Lorita
17 days ago
Haha, I was tempted to go with D) Requirements gap, just to be that guy who picks the weird answer. But B) Late delivery is the correct choice here.
upvoted 0 times
...
Candra
20 days ago
Hmm, I was stuck between B) Late delivery and C) Do not achieve requirements. But B) is the more direct penalty for not meeting the project timeline.
upvoted 0 times
Lourdes
3 days ago
I agree, B) Late delivery is a more direct penalty for not meeting the project timeline.
upvoted 0 times
...
...
Slyvia
27 days ago
I was going to say A) Over budget, but that doesn't quite fit the description of a 'negative incentive'. B) Late delivery makes more sense.
upvoted 0 times
Geoffrey
19 days ago
Late delivery makes more sense.
upvoted 0 times
...
...
Margret
1 months ago
B) Late delivery seems like the obvious answer here. Liquidated damages are a way to incentivize on-time project completion.
upvoted 0 times
Sunshine
2 days ago
B) Late delivery seems like the obvious answer here. Liquidated damages are a way to incentivize on-time project completion.
upvoted 0 times
...
...
Ashley
2 months ago
I believe it's important to have liquidated damages to ensure timely delivery.
upvoted 0 times
...
Vanda
2 months ago
I agree with Eleni, it's a penalty for not meeting the deadline.
upvoted 0 times
...
Eleni
2 months ago
I think liquidated damages are for late delivery.
upvoted 0 times
...

Save Cancel