Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft PL-300 Exam - Topic 2 Question 17 Discussion

Actual exam question for Microsoft's PL-300 exam
Question #: 17
Topic #: 2
[All PL-300 Questions]

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.

You have a Power BI report that imports a date table and a sales table from an Azure SQL database data source. The sales table has the following date foreign keys:

Due Date

Order Date

Delivery Date

You need to support the analysis of sales over time based on all the date foreign keys.

Solution: For each date foreign key, you add inactive relationships between the sales table and the date table.

Does this meet the goal?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Barney
4 months ago
Sounds right, but I’d double-check the model first!
upvoted 0 times
...
Magda
4 months ago
Wait, can you really analyze all those dates like that?
upvoted 0 times
...
Kathryn
5 months ago
I’m not so sure about that. Inactive relationships can complicate things.
upvoted 0 times
...
Shawnna
5 months ago
Totally agree, this should work!
upvoted 0 times
...
Arlette
5 months ago
Inactive relationships can be used for multiple date fields.
upvoted 0 times
...
Mireya
5 months ago
I think the solution might be correct since it allows for flexibility in using different date fields, but I’m worried about how it affects filtering and context in the report.
upvoted 0 times
...
Kenneth
5 months ago
I feel like we discussed how inactive relationships can be useful for certain measures, but I’m not sure if they would allow for proper analysis over time in this case.
upvoted 0 times
...
Lajuana
5 months ago
This reminds me of a practice question where we had to manage multiple date fields. I think using inactive relationships could work, but I’m not confident it meets the goal completely.
upvoted 0 times
...
Luis
5 months ago
I'm not entirely sure if adding inactive relationships is the right approach. I remember something about needing active relationships for certain calculations.
upvoted 0 times
...
Delmy
6 months ago
Hmm, this seems straightforward. I think option D is the way to go - creating a new virtual environment and installing the package there. That way, it's isolated from the main codebase.
upvoted 0 times
...
Brigette
6 months ago
I'm a bit confused by this question. I know Scrum has rules, but I'm not sure which one is relevant for Sprint duration specifically.
upvoted 0 times
...
Junita
6 months ago
Hmm, this seems like a tricky one. I'll need to carefully review the options and think through the potential issues with the voicemail system and SCCP routing.
upvoted 0 times
...

Save Cancel