Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft MB-335 Exam - Topic 2 Question 32 Discussion

Actual exam question for Microsoft's MB-335 exam
Question #: 32
Topic #: 2
[All MB-335 Questions]

You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.

A machine in the facility is defective and must be closed for repairs for the next two days.

You need to configure the resource calendar to close the resource for production for the next two days.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Katie
4 months ago
I’m with C too, it’s the most precise solution!
upvoted 0 times
...
Halina
4 months ago
Wait, can we really just change the calendar for two days?
upvoted 0 times
...
Jeffrey
4 months ago
Definitely not A, that won't close the resource properly.
upvoted 0 times
...
Brendan
4 months ago
I think B is better since it affects the whole production schedule.
upvoted 0 times
...
Valene
5 months ago
Option C seems like the right move for a specific resource.
upvoted 0 times
...
Berry
5 months ago
I’m leaning towards option D because it talks about the resource group, but I need to double-check if that’s the right approach for this scenario.
upvoted 0 times
...
Bok
5 months ago
I feel like option B could be correct since it mentions the production calendar, but I’m not entirely confident about it.
upvoted 0 times
...
Krissy
5 months ago
I remember a practice question where we had to close a resource for maintenance, and I think we adjusted the calendar directly for that resource.
upvoted 0 times
...
Carline
5 months ago
I think we might need to change the calendar for the specific resource, but I'm not sure if it's option A or C.
upvoted 0 times
...
Carin
5 months ago
I'm a little confused by this one. Do I need to do something at the resource level or the calendar level? I'm leaning towards A, but I want to make sure I fully understand the requirements before answering.
upvoted 0 times
...
Eulah
5 months ago
Okay, I've got this. The key is that the question says the resource uses the same production calendar as all the other resources. So I'm going to go with B - navigate to the calendar used for production and close the next two days.
upvoted 0 times
...
Edgar
5 months ago
Hmm, I'm a bit unsure about this one. I'm debating between B and C. I'll have to think it through carefully to make sure I get the right approach.
upvoted 0 times
...
Hyman
6 months ago
This seems pretty straightforward. I think the answer is C - configure a calendar deviation on the resource to set it to closed for the next two days.
upvoted 0 times
...
Layla
6 months ago
Hmm, this seems like a tricky one. I'll need to think carefully about the key design principles for a hierarchical core-distribution-access network model.
upvoted 0 times
...
Blythe
1 year ago
Haha, I can just imagine the chaos if we closed the whole production calendar for a single machine. Might as well just shut the whole place down for two days! Option C is the clear winner.
upvoted 0 times
...
Lauryn
1 year ago
I agree with Mirta. C is definitely the correct answer here. Closing the entire production calendar seems a bit overkill for a single machine issue.
upvoted 0 times
...
Mirta
1 year ago
Option C seems like the way to go. Configuring a calendar deviation on the resource is the most direct approach to close it for the next two days.
upvoted 0 times
Dorothy
1 year ago
Yeah, option C is definitely the best choice in this scenario. It's straightforward and effective.
upvoted 0 times
...
German
1 year ago
I think I'll go with option C as well. It just makes sense to use a calendar deviation for this.
upvoted 0 times
...
Timmy
1 year ago
I agree, it's the most efficient way to handle the situation.
upvoted 0 times
...
Jolanda
1 year ago
Option C seems like the way to go. Configuring a calendar deviation on the resource is the most direct approach to close it for the next two days.
upvoted 0 times
...
...
Ona
1 year ago
I'm not sure, but I think option B could also work.
upvoted 0 times
...
Tonette
2 years ago
I agree with Adela, option C makes the most sense.
upvoted 0 times
...
Adela
2 years ago
I think the correct answer is C.
upvoted 0 times
...

Save Cancel