A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Krissy
3 days ago
Or we could create a resource group for each length. That way we can manage them more efficiently.
upvoted 0 times
...
Abel
4 days ago
I don't think that's necessary. Creating a resource for each length might be more effective.
upvoted 0 times
...
Kerry
5 days ago
What about configuring the Data/Hour option on the Capacity unit field on the resource?
upvoted 0 times
...
Krissy
6 days ago
That sounds like a good idea. It would help us schedule the cutting machines better.
upvoted 0 times
...
Abel
7 days ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
Reiko
16 hours ago
D) Create a resource group for each length.
upvoted 0 times
...
Jess
2 days ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
...