A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rebbecca
11 months ago
I think creating a resource group for each length would also work. It helps in managing resources effectively.
upvoted 0 times
...
Mira
11 months ago
I think creating a resource for each length might be too rigid. Building capability seems more flexible.
upvoted 0 times
...
Sabra
11 months ago
What about creating a resource for each length? Wouldn't that be more specific?
upvoted 0 times
...
Julio
12 months ago
I agree with It makes sense to have the resources configured based on the different product lengths.
upvoted 0 times
...
Mira
12 months ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Krissy
1 years ago
Or we could create a resource group for each length. That way we can manage them more efficiently.
upvoted 0 times
...
Abel
1 years ago
I don't think that's necessary. Creating a resource for each length might be more effective.
upvoted 0 times
...
Kerry
1 years ago
What about configuring the Data/Hour option on the Capacity unit field on the resource?
upvoted 0 times
...
Krissy
1 years ago
That sounds like a good idea. It would help us schedule the cutting machines better.
upvoted 0 times
...
Abel
1 years ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
Dominga
12 months ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Reiko
12 months ago
D) Create a resource group for each length.
upvoted 0 times
...
Jess
1 years ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
...