Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam MB-335 Topic 2 Question 18 Discussion

Actual exam question for Microsoft's MB-335 exam
Question #: 18
Topic #: 2
[All MB-335 Questions]

A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Rebbecca
1 years ago
I think creating a resource group for each length would also work. It helps in managing resources effectively.
upvoted 0 times
...
Mira
1 years ago
I think creating a resource for each length might be too rigid. Building capability seems more flexible.
upvoted 0 times
...
Sabra
1 years ago
What about creating a resource for each length? Wouldn't that be more specific?
upvoted 0 times
...
Julio
1 years ago
I agree with It makes sense to have the resources configured based on the different product lengths.
upvoted 0 times
...
Mira
1 years ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Krissy
1 years ago
Or we could create a resource group for each length. That way we can manage them more efficiently.
upvoted 0 times
...
Abel
1 years ago
I don't think that's necessary. Creating a resource for each length might be more effective.
upvoted 0 times
...
Kerry
1 years ago
What about configuring the Data/Hour option on the Capacity unit field on the resource?
upvoted 0 times
...
Krissy
1 years ago
That sounds like a good idea. It would help us schedule the cutting machines better.
upvoted 0 times
...
Abel
1 years ago
I think we should build capability related to length and assign to the appropriate resources.
upvoted 0 times
Dominga
1 years ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
Reiko
1 years ago
D) Create a resource group for each length.
upvoted 0 times
...
Jess
1 years ago
A) Build capability related to length and assign to the appropriate resources.
upvoted 0 times
...
...

Save Cancel