ISTQB ATTA Exam - Topic 2 Question 109 Discussion

Actual exam question for ISTQB's ATTA exam
Question #: 109
Topic #: 2
[All ATTA Questions]

Part 1 "Test Techniques various"

As part of a risk analysis, technical risks are analyzed. Which TWO factors influence technical risk? 1 credit [K2]

Show Suggested Answer Hide Answer
Suggested Answer: A, C

Contribute your Thoughts:

0/2000 characters
Barabara
5 months ago
Lack of reasonable workaround is crucial for assessing risk.
upvoted 0 times
...
Maryann
5 months ago
I think interfacing issues are a big factor too!
upvoted 0 times
...
Renea
5 months ago
Complexity of technology definitely impacts risk.
upvoted 0 times
...
Reuben
6 months ago
Surprised that damage to image isn't considered a top risk!
upvoted 0 times
...
Crissy
6 months ago
Frequency of use? Not sure that’s a major risk factor.
upvoted 0 times
...
Hermila
6 months ago
I definitely recall that complexity and integration issues are key factors in technical risk analysis.
upvoted 0 times
...
Janine
6 months ago
I'm a bit confused. I feel like lack of reasonable workaround could influence technical risk, but I'm not sure about the other one.
upvoted 0 times
...
Twana
7 months ago
I remember practicing a question about technical risks, and I think frequency of use might play a role too.
upvoted 0 times
...
Misty
7 months ago
I think the complexity of technology is definitely a factor, but I'm not sure about the second one. Maybe interfacing issues?
upvoted 0 times
...
Barbra
7 months ago
I feel confident about this one. Complexity and integration are the clear choices that influence technical risk the most.
upvoted 0 times
...
Bulah
7 months ago
Ugh, risk analysis questions can be tricky. Let me think this through step-by-step to make sure I don't miss anything.
upvoted 0 times
...
Hubert
7 months ago
Okay, I've got this. Complexity and integration are the two key factors that impact technical risk, so I'll select those.
upvoted 0 times
...
Ernie
8 months ago
Hmm, I'm a bit unsure about this one. I'll need to carefully read through the options and think about which two factors are most relevant for technical risk.
upvoted 0 times
...
Lai
8 months ago
This question seems straightforward. I'll focus on the key factors that influence technical risk, like complexity of technology and integration issues.
upvoted 0 times
...
Felicidad
1 year ago
I believe lack of reasonable workaround and damage to image also play a role in determining technical risk.
upvoted 0 times
...
Chandra
1 year ago
I agree with Jeanice. Those factors can definitely impact the technical risk in a project.
upvoted 0 times
...
Jeanice
1 year ago
I think complexity of technology and interfacing and integration issues influence technical risk.
upvoted 0 times
...
Antonio
1 year ago
Hmm, I'd go with A and C as well. Gotta love those technical risks, am I right? It's like a choose-your-own-adventure game, but with more spreadsheets and less adventure.
upvoted 0 times
Van
12 months ago
It's important to have a solid plan in place to mitigate those technical risks.
upvoted 0 times
...
Gregoria
12 months ago
Definitely, those two factors can really impact the success of a project.
upvoted 0 times
...
Reuben
1 year ago
I agree, the complexity of technology and interfacing issues are crucial factors to consider.
upvoted 0 times
...
Jean
1 year ago
Yeah, technical risks can really make or break a project.
upvoted 0 times
...
...
Carrol
1 year ago
Let's see... Complexity and integration issues, that makes sense. The other options seem a bit off-topic. Maybe the test writers were just trying to trip us up with those distractors. Nice try, but I'm on to you!
upvoted 0 times
Lajuana
1 year ago
Yeah, the other options seem like they could be important in other contexts, but not specifically related to technical risk.
upvoted 0 times
...
Lavonne
1 year ago
I agree, complexity and integration issues are definitely key factors in technical risk.
upvoted 0 times
...
...
Myra
1 year ago
I agree with Cathern. A and C are the obvious choices here. Though I have to say, D and E sound like excuses my grandma would make for not using the microwave.
upvoted 0 times
...
Cathern
1 year ago
Definitely A and C. The complexity of the technology and the integration challenges are key factors that influence technical risk. Damage to image and lack of workaround are more like business risks.
upvoted 0 times
Ahmed
12 months ago
It's important to consider all factors when analyzing technical risks.
upvoted 0 times
...
Iraida
12 months ago
I think D and E are more related to business risks rather than technical risks.
upvoted 0 times
...
Larue
12 months ago
Yeah, complexity of technology and integration issues can really impact the project.
upvoted 0 times
...
Joni
1 year ago
I agree, A and C are definitely the key factors for technical risk.
upvoted 0 times
...
Kerry
1 year ago
It's important to consider all factors when analyzing technical risks.
upvoted 0 times
...
Roselle
1 year ago
I think D and E are more related to business risks rather than technical risks.
upvoted 0 times
...
Eulah
1 year ago
Yeah, complexity of technology and integration issues can really impact the project.
upvoted 0 times
...
Lorean
1 year ago
I agree, A and C are definitely the key factors for technical risk.
upvoted 0 times
...
...