New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

iSQI CTFL_Syll_4.0 Exam - Topic 5 Question 39 Discussion

Actual exam question for iSQI's CTFL_Syll_4.0 exam
Question #: 39
Topic #: 5
[All CTFL_Syll_4.0 Questions]

Following a risk-based testing approach you have designed 10 tests to cover a product risk with a high-risk level. You want to estimate, adopting the three-point test estimation technique, the test effort required to reduce the risk level to zero by executing those 10 tests. You made the following three initial estimates:

* most optimistic = 6 person hours

* most likely = 30 person hours

* most pessimistic = 54 person hours

Based only on the given information, which of the following answers about the three-point test estimation technique applied to this problem is true?

Show Suggested Answer Hide Answer
Suggested Answer: A

The three-point test estimation technique is a method of estimating the test effort based on three initial estimates: the most optimistic, the most likely, and the most pessimistic. The technique uses a weighted average of these three estimates to calculate the final estimate, which is also known as the expected value. The formula for the expected value is:

Expected value = (most optimistic + 4 * most likely + most pessimistic) / 6

Using the given values, the expected value is:

Expected value = (6 + 4 * 30 + 54) / 6 Expected value = 30 person hours

However, the expected value is not the only factor to consider when estimating the test effort. The technique also calculates the standard deviation, which is a measure of the variability or uncertainty of the estimates. The formula for the standard deviation is:

Standard deviation = (most pessimistic - most optimistic) / 6

Using the given values, the standard deviation is:

Standard deviation = (54 - 6) / 6 Standard deviation = 8 person hours

The standard deviation can be used to determine a range of possible values for the test effort, based on a certain level of confidence. For example, using a 68% confidence level, the range is:

Expected value standard deviation

Using the calculated values, the range is:

30 8 person hours

Therefore, the final estimate is between 22 person hours and 38 person hours, which is option A.


Contribute your Thoughts:

0/2000 characters
Sherill
2 months ago
The range should be wider than just 6 to 54 hours.
upvoted 0 times
...
Samuel
3 months ago
Definitely not just the most likely estimate!
upvoted 0 times
...
Rashida
3 months ago
Wait, how can we be sure it’s between 22 and 38 hours? Sounds off.
upvoted 0 times
...
Ezekiel
3 months ago
The final estimate is calculated using the three-point technique, not just the most likely.
upvoted 0 times
...
Pearline
3 months ago
I think the final estimate should be around 30 hours, but it’s not exact.
upvoted 0 times
...
Ivan
3 months ago
If I remember correctly, we usually calculate the final estimate using the average of the three values, so it shouldn't be exactly 30 hours.
upvoted 0 times
...
Vonda
4 months ago
I feel like the most likely estimate is important, but I don't think it means the final estimate is just 30 hours.
upvoted 0 times
...
Cecilia
4 months ago
I think the final estimate should be between the optimistic and pessimistic values, but I can't recall the exact formula we used in practice.
upvoted 0 times
...
Val
4 months ago
I remember the three-point estimation technique involves calculating a weighted average, but I'm not sure how to apply it here.
upvoted 0 times
...
Louisa
4 months ago
Alright, I've got this. The three-point estimation formula is (Optimistic + 4 x Most Likely + Pessimistic) / 6. Plugging in the values, that gives us a final estimate between 22 and 38 person hours. The answer is A.
upvoted 0 times
...
Dick
4 months ago
Wait, I thought the three-point technique used a formula to calculate the final estimate, not just the average. I'm a bit confused on the details, but I think the answer is A.
upvoted 0 times
...
Queenie
5 months ago
I remember learning about the three-point estimation technique in class. I believe the final estimate is calculated by taking the average of the three initial estimates, which would make the answer D.
upvoted 0 times
...
Josphine
5 months ago
Okay, let's see. The question gives us the most optimistic, most likely, and most pessimistic estimates. I think the final answer has to be somewhere between those values, but I'm not sure exactly how to calculate it.
upvoted 0 times
...
Raul
5 months ago
Hmm, this seems like a tricky one. I'll need to think through the three-point estimation technique carefully to figure out the right answer.
upvoted 0 times
...
Delmy
7 months ago
I see your point, but I still think it's between 22 person hours and 38 person hours.
upvoted 0 times
...
Vilma
7 months ago
I'm not sure, but I think the final estimate is between 6 person hours and 54 person hours.
upvoted 0 times
...
Elsa
7 months ago
I bet the test designers are just trying to keep us on our toes. Probably the right answer is something completely unexpected, like 42 person hours. That's the answer to life, the universe, and everything, after all!
upvoted 0 times
Dallas
5 months ago
C) The final estimate is between 6 person hours and 54 person hours
upvoted 0 times
...
Kenneth
6 months ago
A) The final estimate is between 22 person hours and 38 person hours
upvoted 0 times
...
...
Otis
7 months ago
Option C is the only one that includes the full range of the initial estimates. That's gotta be the right answer, right? Unless the test designers are trying to trick us...
upvoted 0 times
...
Aleisha
7 months ago
Hmm, I'm torn between A and D. But I think D makes more sense since the question specifically mentions the three-point technique.
upvoted 0 times
Justine
5 months ago
Yes, D makes sense because the final estimate is calculated using the three initial estimates in this technique.
upvoted 0 times
...
Loreen
5 months ago
I agree, D seems to be the most logical choice based on the information provided.
upvoted 0 times
...
Carey
7 months ago
I think D is correct because the three-point technique uses the arithmetic mean of the three initial estimates.
upvoted 0 times
...
...
Dick
8 months ago
I'm going with Option D. The three-point technique uses the arithmetic mean, so the final estimate is 30 person hours.
upvoted 0 times
Kyoko
7 months ago
Yes, I agree. The three-point technique uses the arithmetic mean of the three initial estimates.
upvoted 0 times
...
Cathrine
7 months ago
I think Option D is correct. The final estimate is 30 person hours.
upvoted 0 times
...
...
Lenita
8 months ago
I believe the final estimate is exactly 30 person hours because the technique uses the initial most likely estimate as the final estimate.
upvoted 0 times
...
Yolande
8 months ago
Option A seems reasonable, the final estimate should be the average of the three initial estimates.
upvoted 0 times
Elin
7 months ago
The final estimate should be between 6 person hours and 54 person hours based on the three-point test estimation technique.
upvoted 0 times
...
Keneth
7 months ago
I believe the final estimate is exactly 30 person hours because that's the most likely estimate.
upvoted 0 times
...
Sheridan
8 months ago
I think the final estimate is between 22 person hours and 38 person hours.
upvoted 0 times
...
...
Delmy
8 months ago
I think the final estimate is between 22 person hours and 38 person hours.
upvoted 0 times
...

Save Cancel