Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

IIBA Exam CBAP Topic 1 Question 82 Discussion

Actual exam question for IIBA's CBAP exam
Question #: 82
Topic #: 1
[All CBAP Questions]

Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Mozell
12 hours ago
The project schedule network diagram is the way to go! It's like a roadmap for your project, showing the order of all the tasks.
upvoted 0 times
...
Renea
2 days ago
I'm not sure, but I think C) Arrow diagramming method could also be a correct choice.
upvoted 0 times
...
Dexter
4 days ago
I agree with Antonio, because project schedule network diagram shows the sequence of project activities.
upvoted 0 times
...
Antonio
5 days ago
I think the answer is B) Project schedule network diagram.
upvoted 0 times
...

Save Cancel