Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 14 Question 108 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 108
Topic #: 14
[All PPM-001 Questions]

Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Trevor
27 days ago
As someone who's been on plenty of projects, I can tell you that missing dependencies are the bane of our existence. D is the only logical answer here.
upvoted 0 times
Sylvie
13 hours ago
Looks like we need to make sure activity E is completed before starting activity F.
upvoted 0 times
...
Sherrell
18 days ago
Definitely, it's important to catch those early on to avoid delays.
upvoted 0 times
...
Cherri
20 days ago
I agree, missing dependencies can really throw off a project timeline.
upvoted 0 times
...
...
Gracie
1 months ago
Woah, talk about a last-minute curveball! This team member better not make a habit of forgetting things. D all the way, no doubt about it.
upvoted 0 times
Blair
13 days ago
User 2: Yeah, that new dependency definitely throws a wrench in the timeline.
upvoted 0 times
...
Margart
20 days ago
User 1: I agree, D would delay activity F.
upvoted 0 times
...
...
Julio
1 months ago
Hold up, is this a trick question? I'm leaning towards D, but I wouldn't put it past them to try and confuse us. Better double-check the chart just to be sure.
upvoted 0 times
...
Valene
1 months ago
Oh, this is a tricky one. But I'm pretty sure the correct answer is D. Delays are never fun, but at least it's not a communication issue.
upvoted 0 times
Erick
23 days ago
That makes sense, delays can really impact a project.
upvoted 0 times
...
Brinda
1 months ago
I think you're right, D) It would delay activity F.
upvoted 0 times
...
...
Jacob
2 months ago
Ah, I see what they're getting at. The new dependency is going to throw a wrench in the works. Gotta be D, right?
upvoted 0 times
Agustin
1 months ago
User 2: Definitely, that new dependency is going to cause a delay.
upvoted 0 times
...
Kip
1 months ago
User 1: Yeah, you're right. It would delay activity F.
upvoted 0 times
...
...
Brynn
2 months ago
Hmm, I think the correct answer is D. The new dependency between E and F will delay the start of activity F, which could impact the critical path.
upvoted 0 times
...
Yan
2 months ago
But wouldn't it also increase the critical path if activity F is delayed? That could have a big impact on the project.
upvoted 0 times
...
Britt
2 months ago
I agree with you, Jolene. It makes sense that if there's a new dependency, it would affect the project timeline.
upvoted 0 times
...
Jolene
2 months ago
I think if activity F needs the results of activity E before it can begin, it would delay activity F.
upvoted 0 times
...

Save Cancel