Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam PPM-001 Topic 14 Question 108 Discussion

Actual exam question for GAQM's PPM-001 exam
Question #: 108
Topic #: 14
[All PPM-001 Questions]

Based on the chart, while completing the project, a team member tells you that the team forgot something during planning. Activity F needs the results of activity E before it can begin. Taking this new dependency into account, what would be the effect on the project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Jacob
1 days ago
Ah, I see what they're getting at. The new dependency is going to throw a wrench in the works. Gotta be D, right?
upvoted 0 times
...
Brynn
2 days ago
Hmm, I think the correct answer is D. The new dependency between E and F will delay the start of activity F, which could impact the critical path.
upvoted 0 times
...
Yan
11 days ago
But wouldn't it also increase the critical path if activity F is delayed? That could have a big impact on the project.
upvoted 0 times
...
Britt
11 days ago
I agree with you, Jolene. It makes sense that if there's a new dependency, it would affect the project timeline.
upvoted 0 times
...
Jolene
17 days ago
I think if activity F needs the results of activity E before it can begin, it would delay activity F.
upvoted 0 times
...

Save Cancel