GAQM CSM-001 Exam - Topic 5 Question 112 Discussion

More than one Scrum Team is working on a single project or release. How should the Product Backlog be arranged?
B) All Scrum Teams work from a common Product Backlog and integrate their work every sprint
A) A separate Product Backlog is constructed for each Scrum Team. All of the increments are integrated at the end in an integration Sprint
C) Only one Scrum Team should work on Scrum project
D) Scrum Teams should have their separate Product Backlogs

GAQM CSM-001 Exam - Topic 5 Question 112 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 112
Topic #: 5
[All CSM-001 Questions]

More than one Scrum Team is working on a single project or release. How should the Product Backlog be arranged?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

0/2000 characters
Erasmo
4 days ago
I disagree, separate backlogs can help avoid confusion.
upvoted 0 times
...
Aide
10 days ago
I think option B makes the most sense for collaboration.
upvoted 0 times
...
Lynelle
15 days ago
I recall discussing that separate backlogs can lead to misalignment, so I think option D might not be the best choice either.
upvoted 0 times
...
Antonio
20 days ago
I feel like option C is definitely wrong because having only one team wouldn't be effective for larger projects.
upvoted 0 times
...
Gearldine
25 days ago
I'm not entirely sure, but I remember something about separate backlogs causing issues with integration. Maybe option A could be a possibility?
upvoted 0 times
...
Flo
2 months ago
I think option B sounds right since it mentions a common Product Backlog, which aligns with what we practiced about scaling Scrum.
upvoted 0 times
...