The correct sequence of events in using Scrum framework is as follows:
Which statement below best describes the primary objective of the Sprint Retrospective?
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with thefollowing information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number ofSprintrequired to complete product development?
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?