You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
Sol
2 months agoMartina
2 months agoMaynard
2 months agoPedro
2 months agoDenise
2 months agoLarue
3 months agoSilvana
1 months agoRenato
1 months agoNoah
2 months agoTawna
2 months agoJerry
2 months agoJaime
2 months agoRosalind
2 months agoAileen
3 months agoAntonio
3 months agoAngella
3 months agoAleta
2 months agoTashia
2 months agoJosefa
2 months agoMan
2 months agoPrecious
3 months agoMammie
4 months ago