New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM CSM-001 Exam - Topic 4 Question 64 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 64
Topic #: 4
[All CSM-001 Questions]

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Show Suggested Answer Hide Answer
Suggested Answer: C, D, G

Contribute your Thoughts:

0/2000 characters
Elli
3 months ago
Not sure about keeping them for the next Sprint... feels risky.
upvoted 0 times
...
Gennie
3 months ago
I’m surprised they can’t finish those tasks in time!
upvoted 0 times
...
Willie
3 months ago
Placing them back on the backlog seems like a smart move.
upvoted 0 times
...
Marguerita
4 months ago
No way, they should just work the extra hours!
upvoted 0 times
...
Cora
4 months ago
I think they should negotiate with the Product Owner.
upvoted 0 times
...
Pearlene
4 months ago
Keeping the tasks for the next Sprint sounds familiar, but I recall we should prioritize what’s most valuable for the Product Owner. Is that the right approach?
upvoted 0 times
...
Daisy
4 months ago
I feel like placing the two Product Backlog items back onto the backlog could be a safe choice, but I wonder if it would impact the team's velocity.
upvoted 0 times
...
Sherron
4 months ago
I'm not sure if working extra hours is a good idea. I think we talked about how it can lead to burnout and isn't sustainable for the team.
upvoted 0 times
...
Linette
5 months ago
I remember we discussed how important it is to negotiate with the Product Owner about the definition of 'done' in our last class. That might be a good option here.
upvoted 0 times
...
Aimee
5 months ago
Ugh, I'm not sure about this. There are a lot of details to keep track of. I'll need to take my time and really analyze each choice carefully.
upvoted 0 times
...
Nikita
5 months ago
I'm feeling pretty confident about this one. I think option C is the way to go - placing the two incomplete items back on the Product Backlog seems like the most sensible approach.
upvoted 0 times
...
Rosita
5 months ago
Hmm, I'm a bit confused on how to handle the remaining tasks. I'll need to re-read the question and think through the implications of each choice.
upvoted 0 times
...
Naomi
5 months ago
This is a tricky one, but I think I have a strategy. I'll need to carefully consider the options and weigh the pros and cons of each.
upvoted 0 times
...
Ammie
5 months ago
I'm a little confused by all the options here. I think I'll start by trying option A, since it seems the most straightforward. If that doesn't work, I'll move on to the other choices.
upvoted 0 times
...
Maryln
5 months ago
I'm a bit confused by the wording of the question. What exactly does it mean by "unique solution" and "more than one correct solution"? I'll need to read through it a few times to make sure I understand the requirements.
upvoted 0 times
...
Sol
9 months ago
Option D sounds like a great way to start the next Sprint on the wrong foot. Let's be smart and go with C. The Product Owner can always re-prioritize those items for the next Sprint.
upvoted 0 times
...
Martina
10 months ago
Haha, the 'work extra 8 hours' option is a classic. I'm sure the team would love that idea, but it's not sustainable. Placing the incomplete items back on the Product Backlog is the way to go.
upvoted 0 times
Maynard
9 months ago
Yeah, working extra hours is not the best solution. Let's focus on what's sustainable for the team.
upvoted 0 times
...
Pedro
9 months ago
C) The development team should place the two Product Backlog items back onto the Product Backlog
upvoted 0 times
...
Denise
9 months ago
A) The development team should negotiate with the Product Owner on the definition of 'done'.
upvoted 0 times
...
...
Larue
10 months ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout. I think the team should be realistic and move the unfinished items back to the Product Backlog.
upvoted 0 times
Silvana
8 months ago
I think that's a good plan. Let's discuss this with the Product Owner and make the necessary adjustments.
upvoted 0 times
...
Renato
8 months ago
That sounds like a more sustainable approach. We can then prioritize those items in the next Sprint.
upvoted 0 times
...
Noah
9 months ago
I agree, burnout is a real concern. Maybe we should consider option C and move the unfinished items back to the Product Backlog.
upvoted 0 times
...
Tawna
9 months ago
Let's discuss with the Product Owner for clarity.
upvoted 0 times
...
Jerry
9 months ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout.
upvoted 0 times
...
Jaime
9 months ago
Agreed. Moving unfinished items back is more realistic.
upvoted 0 times
...
Rosalind
9 months ago
Option B seems risky. Burnout is a concern.
upvoted 0 times
...
...
Aileen
10 months ago
I agree with option C. Putting the unfinished items back on the Product Backlog is the best way to handle this situation. Maybe the Product Owner can reevaluate the priority of those items for the next Sprint.
upvoted 0 times
...
Antonio
10 months ago
I disagree. We should negotiate with the Product Owner on the definition of 'done' to see if there's any flexibility.
upvoted 0 times
...
Angella
10 months ago
The development team should place the two Product Backlog items back onto the Product Backlog. This is the correct answer as it allows the team to focus on completing the tasks they can finish within the remaining 16 hours and re-evaluate the two incomplete items for the next Sprint.
upvoted 0 times
Aleta
9 months ago
C
upvoted 0 times
...
Tashia
9 months ago
A
upvoted 0 times
...
Josefa
9 months ago
C
upvoted 0 times
...
Man
9 months ago
A
upvoted 0 times
...
...
Precious
10 months ago
I agree with Mammie. It's important to deliver on our commitment to the Product Owner.
upvoted 0 times
...
Mammie
11 months ago
I think we should work the extra 8 hours to complete our commitment.
upvoted 0 times
...

Save Cancel