Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam CSM-001 Topic 4 Question 64 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 64
Topic #: 4
[All CSM-001 Questions]

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Show Suggested Answer Hide Answer
Suggested Answer: C, D, G

Contribute your Thoughts:

Sol
22 days ago
Option D sounds like a great way to start the next Sprint on the wrong foot. Let's be smart and go with C. The Product Owner can always re-prioritize those items for the next Sprint.
upvoted 0 times
...
Martina
24 days ago
Haha, the 'work extra 8 hours' option is a classic. I'm sure the team would love that idea, but it's not sustainable. Placing the incomplete items back on the Product Backlog is the way to go.
upvoted 0 times
Pedro
4 days ago
C) The development team should place the two Product Backlog items back onto the Product Backlog
upvoted 0 times
...
Denise
5 days ago
A) The development team should negotiate with the Product Owner on the definition of 'done'.
upvoted 0 times
...
...
Larue
1 months ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout. I think the team should be realistic and move the unfinished items back to the Product Backlog.
upvoted 0 times
Noah
2 days ago
I agree, burnout is a real concern. Maybe we should consider option C and move the unfinished items back to the Product Backlog.
upvoted 0 times
...
Tawna
5 days ago
Let's discuss with the Product Owner for clarity.
upvoted 0 times
...
Jerry
9 days ago
Option B seems like a risky move. Working extra hours to complete the commitment could lead to burnout.
upvoted 0 times
...
Jaime
18 days ago
Agreed. Moving unfinished items back is more realistic.
upvoted 0 times
...
Rosalind
21 days ago
Option B seems risky. Burnout is a concern.
upvoted 0 times
...
...
Aileen
1 months ago
I agree with option C. Putting the unfinished items back on the Product Backlog is the best way to handle this situation. Maybe the Product Owner can reevaluate the priority of those items for the next Sprint.
upvoted 0 times
...
Antonio
2 months ago
I disagree. We should negotiate with the Product Owner on the definition of 'done' to see if there's any flexibility.
upvoted 0 times
...
Angella
2 months ago
The development team should place the two Product Backlog items back onto the Product Backlog. This is the correct answer as it allows the team to focus on completing the tasks they can finish within the remaining 16 hours and re-evaluate the two incomplete items for the next Sprint.
upvoted 0 times
Aleta
10 days ago
C
upvoted 0 times
...
Tashia
11 days ago
A
upvoted 0 times
...
Josefa
18 days ago
C
upvoted 0 times
...
Man
20 days ago
A
upvoted 0 times
...
...
Precious
2 months ago
I agree with Mammie. It's important to deliver on our commitment to the Product Owner.
upvoted 0 times
...
Mammie
2 months ago
I think we should work the extra 8 hours to complete our commitment.
upvoted 0 times
...

Save Cancel