You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
Sol
22 days agoMartina
24 days agoPedro
4 days agoDenise
5 days agoLarue
1 months agoNoah
2 days agoTawna
5 days agoJerry
9 days agoJaime
18 days agoRosalind
21 days agoAileen
1 months agoAntonio
2 months agoAngella
2 months agoAleta
10 days agoTashia
11 days agoJosefa
18 days agoMan
20 days agoPrecious
2 months agoMammie
2 months ago