Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GAQM Exam CSM-001 Topic 4 Question 64 Discussion

Actual exam question for GAQM's CSM-001 exam
Question #: 64
Topic #: 4
[All CSM-001 Questions]

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Show Suggested Answer Hide Answer
Suggested Answer: C, D, G

Contribute your Thoughts:

Antonio
3 days ago
I disagree. We should negotiate with the Product Owner on the definition of 'done' to see if there's any flexibility.
upvoted 0 times
...
Angella
4 days ago
The development team should place the two Product Backlog items back onto the Product Backlog. This is the correct answer as it allows the team to focus on completing the tasks they can finish within the remaining 16 hours and re-evaluate the two incomplete items for the next Sprint.
upvoted 0 times
...
Precious
6 days ago
I agree with Mammie. It's important to deliver on our commitment to the Product Owner.
upvoted 0 times
...
Mammie
13 days ago
I think we should work the extra 8 hours to complete our commitment.
upvoted 0 times
...

Save Cancel