A System Engineer is working on an implementation of the VxBlock 1000. What is a required task in the final implementation step during the Deployment Phase?
B) Execute the agreed-upon test plan
A) Verify system physical configuration against LCS
C) Configure Cisco Smart Call Home
D) Connect to individual Element Managers

Dell EMC D-VXB-DY-A-24 Exam - Topic 3 Question 41 Discussion

Actual exam question for Dell EMC's D-VXB-DY-A-24 exam
Question #: 41
Topic #: 3
[All D-VXB-DY-A-24 Questions]

A System Engineer is working on an implementation of the VxBlock 1000. What is a required task in the final implementation step during the Deployment Phase?

Show Suggested Answer Hide Answer
Suggested Answer: B

Review Deployment Phase Requirements: The final implementation step during the Deployment Phase of a VxBlock 1000 involves ensuring that the system is functioning as expected1.

Identify Required Task: A critical task in this step is to execute the test plan that was agreed upon during the planning phase1.

Understand the Importance of Test Plan Execution: Executing the test plan is essential to validate that all components of the VxBlock 1000 are working correctly and that the system meets the customer's requirements1.

Reference Official Dell Documentation: The Official Dell VxBlock Deploy Achievement document outlines the importance of executing the test plan as a required task in the final implementation step during the Deployment Phase1.