Robyn has created a contract for a construction project and has used "The Red Book."

Q: Which professional organization is responsible for creating this contract?

Answer Options:

Show Suggested Answer Hide Answer
Suggested Answer: D

The Red Book is part of the FIDIC 'Rainbow Suite' of contracts (p.40). FIDIC contracts are categorized by color, each serving a specific purpose in construction and engineering projects. [P.40]