New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIPS L5M8 Exam - Topic 1 Question 9 Discussion

Actual exam question for CIPS's L5M8 exam
Question #: 9
Topic #: 1
[All L5M8 Questions]

Dependencies are the relation between tasks and dictate the order in which tasks are approached. Claudia is running a tender under the Public Contracts Regulations 2015, and there is a 10-day standstill period before she can draft the contract. What type of dependency is this?

Show Suggested Answer Hide Answer
Suggested Answer: A

A mandatory dependency is legally or logically required --- in this case, the statutory 10-day ''standstill'' under public procurement law. Other types: external (outside factors), discretionary (team choice), internal (organisational processes).


Contribute your Thoughts:

0/2000 characters
Art
5 days ago
I'm not entirely sure, but I remember something about regulatory dependencies in our practice questions. This seems similar.
upvoted 0 times
...
Coletta
10 days ago
I think this might be a finish-to-start dependency since the standstill period has to finish before the contract drafting can start.
upvoted 0 times
...
Jacqueline
15 days ago
Okay, I think I've got it. The 10-day standstill period before drafting the contract is a temporal dependency. It's a time-based constraint that has to be satisfied before the next task can begin. This is a common type of dependency in project management, so I feel pretty confident about this answer.
upvoted 0 times
...
Aide
20 days ago
I'm a bit unsure about this one. Is the 10-day standstill period a legal requirement, or is it just a best practice? If it's a legal requirement, then I think it would be considered a mandatory dependency. But if it's more of a guideline, then it might be a discretionary dependency. I'll need to think about this a bit more.
upvoted 0 times
...
Lezlie
26 days ago
I'm pretty confident this is a temporal dependency. The 10-day standstill period creates a time-based constraint that has to be satisfied before the next task can begin. Knowing the different types of dependencies is key for managing project timelines effectively.
upvoted 0 times
...
Pete
1 month ago
Okay, let's think this through. The question mentions a 10-day standstill period before drafting the contract, so that must be some kind of dependency that dictates the order of tasks. I'm guessing it's a temporal dependency, where one task has to happen before another can start.
upvoted 0 times
...
Matilda
1 month ago
Hmm, this seems like a question about project dependencies. I think the 10-day standstill period before drafting the contract is a type of dependency, but I'm not sure which one exactly.
upvoted 0 times
...

Save Cancel