Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

CIMAPRO19-P03-1 Exam - Topic 6 Question 96 Discussion

Actual exam question for CIMA's CIMAPRO19-P03-1 exam
Question #: 96
Topic #: 6
[All CIMAPRO19-P03-1 Questions]

A project has been evaluated on the basis that it will cost $22 million and will have a net present value of $4.3 million The project has commenced and $5 millionof the $22 million has been invested. A problem has been discovered that will cost an additional $4.5 million to rectify. The $4.5 million will be payable immediately. What is theNPV of continuing with this project?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Shonda
3 months ago
So, the new NPV is $4.3M - $4.5M = -$0.2M.
upvoted 0 times
...
Leontine
3 months ago
Adding $4.5 million costs a lot!
upvoted 0 times
...
Roxanne
4 months ago
Totally makes sense, negative NPV means it's a bad move now.
upvoted 0 times
...
Zoila
4 months ago
Wait, how can it be negative after spending $5M already?
upvoted 0 times
...
Lemuel
4 months ago
The initial NPV was $4.3 million.
upvoted 0 times
...
Madelyn
4 months ago
I feel like the answer might be D, but I'm not entirely confident. I think we need to subtract the $4.5 million from the original NPV, but I need to double-check my calculations.
upvoted 0 times
...
Ira
4 months ago
If the project originally had an NPV of $4.3 million, and we add the $4.5 million cost, I think it might drop below zero, but I can't recall the exact calculation.
upvoted 0 times
...
Rasheeda
5 months ago
This seems similar to a practice question we did about sunk costs. I think we shouldn't consider the $5 million already spent, but I'm a bit confused about how to adjust the NPV after the extra $4.5 million.
upvoted 0 times
...
Shalon
5 months ago
I remember that the NPV is calculated by taking the initial investment and subtracting any additional costs, but I'm not sure how to factor in the already invested amount.
upvoted 0 times
...
Na
5 months ago
Alright, let's see here. The key is figuring out how the extra $4.5 million impacts the overall NPV. I'm feeling pretty confident I can get the right answer.
upvoted 0 times
...
Tyra
5 months ago
Okay, I've got this. I just need to update the total project cost and then recalculate the NPV. Shouldn't be too bad.
upvoted 0 times
...
Novella
5 months ago
Hmm, I'm a bit confused on how to calculate the new NPV with the additional $4.5 million cost. I'll need to review the formula.
upvoted 0 times
...
Wade
6 months ago
This looks like a tricky one, but I think I can work through it step-by-step.
upvoted 0 times
...
Clorinda
7 months ago
Wait, if we've already spent $5 million and there's an additional $4.5 million needed, then the total cost is $9.5 million. Subtracting that from the original $4.3 million NPV would give us a negative NPV, so I'm going with B) -$0.2 million.
upvoted 0 times
...
Jacinta
7 months ago
Okay, so we have a project that has already cost $5 million, and now there's an additional $4.5 million needed to fix a problem. The original NPV was $4.3 million, so I'm thinking the answer is D) $4.8 million.
upvoted 0 times
Chau
6 months ago
I think you're right, the NPV of continuing with the project would be $4.8 million.
upvoted 0 times
...
Minna
6 months ago
I think the answer is D) $4.8 million.
upvoted 0 times
...
...
Tracie
7 months ago
I think the NPV will be negative if we continue with the project.
upvoted 0 times
...

Save Cancel