CIMA Exam CIMAPRA19-E02-1 Topic 7 Question 68 Discussion

Actual exam question for CIMA's CIMAPRA19-E02-1 exam
Question #: 68
Topic #: 7
[All CIMAPRA19-E02-1 Questions]

The Board of organisation Y has authorised an upgrade toitscomputerised finance system.

The Finance Director, X, has been tasked with managing this project. X has been requested to consult with stakeholders, in order that a Project Initiation Document (PID) may be produced.

What arethe TWO main uses of a PID?

Show Suggested Answer Hide Answer
Suggested Answer: A, B

Contribute your Thoughts:

Loreta
8 days ago
Woah, this question is testing my project management knowledge! Let's see, a PID should provide a solid foundation for the project and help with ongoing management. I'll go with C and D.
upvoted 0 times
...
Theodora
9 days ago
Ah, a PID is like the instruction manual for a project. It's gotta have all the important details to keep things on track. I'd say B and D are the way to go here.
upvoted 0 times
...
Iesha
11 days ago
Hmm, this question is asking about the main uses of a Project Initiation Document (PID). I think I'll go with options C and D - they seem to cover the key purposes of a PID quite well.
upvoted 0 times
...
Twana
1 months ago
I also think that the PID helps to establish a solid foundation for the project before making any major commitments. It's crucial for ensuring the project's success.
upvoted 0 times
...
Markus
1 months ago
I agree with Alberto. It's important to have a structured approach to the project and a document to refer back to for managing progress and changes.
upvoted 0 times
...
Alberto
1 months ago
I think the main uses of a PID are to ensure the project is broken down into work packages and to act as a base document for managing the project.
upvoted 0 times
...