Upon review of all consultants' drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?
Option B seems like the best choice here. Coordinating the change with all parties through a change order is the most professional and transparent approach.
I feel like providing dimensions and a notation could work, but it might not be enough if the contractor has already started work based on the original plans.
I remember a similar practice question where we had to decide if the contractor had to follow the design documents strictly. I think option D might be too risky.
I'm a bit confused - is the designer responsible for the mechanical drawings, or should they just be coordinating with the mechanical engineer? I'm not sure if C is the right call.
Okay, I think the key here is coordinating the change with all the relevant parties. Option B seems like the best approach to make sure everyone is on the same page.
Vanna
9 hours agoAlease
6 days agoNobuko
11 days agoHelaine
16 days agoLakeesha
21 days agoMaryanne
26 days agoLang
1 month agoElly
1 month agoJacinta
1 month agoLavina
2 months agoLinn
2 months agoNoel
2 months agoJospeh
2 months agoDiane
2 months agoBrigette
3 months agoAntonio
3 months agoJenifer
3 months agoMilly
3 months agoJeniffer
2 months ago