Upon review of all consultants' drawings, the designer notices that the placement of a water closet is not consistent with the contract documents. What should the designer do?
Option B seems like the best choice here. Coordinating the change with all parties through a change order is the most professional and transparent approach.
I feel like providing dimensions and a notation could work, but it might not be enough if the contractor has already started work based on the original plans.
I remember a similar practice question where we had to decide if the contractor had to follow the design documents strictly. I think option D might be too risky.
I'm a bit confused - is the designer responsible for the mechanical drawings, or should they just be coordinating with the mechanical engineer? I'm not sure if C is the right call.
Okay, I think the key here is coordinating the change with all the relevant parties. Option B seems like the best approach to make sure everyone is on the same page.
Lashaunda
1 month agoJudy
2 months agoRobt
2 months agoAlverta
2 months agoMalika
2 months agoJean
2 months agoAileen
2 months agoVanna
3 months agoAlease
3 months agoNobuko
3 months agoHelaine
4 months agoLakeesha
4 months agoMaryanne
4 months agoLang
4 months agoElly
4 months agoJacinta
4 months agoLavina
5 months agoLinn
5 months agoNoel
5 months agoJospeh
5 months agoDiane
5 months agoBrigette
6 months agoAntonio
6 months agoJenifer
6 months agoMilly
6 months agoArmanda
20 days agoKristine
26 days agoMarge
1 month agoAmmie
1 month agoJeniffer
5 months ago