Assume you are managing the system testing execution phase of a project.
The system test execution period for that project is scheduled for eighteen weeks and the release date is scheduled at the end of system testing.
During the sixth week of system test execution, at the staff meeting, the project manager informs you that the project deadlines are changed and the release date that is only three weeks ahead.
This new release will not allow the completion of the system tests. Suppose also that you have followed a risk-driven test approach for this project.
Which of the following statements represents the worst way to lead your test team in the next three weeks?
Number of correct responses: 1
Fabiola
10 months agoSue
10 months agoArlean
10 months agoTresa
10 months agoJutta
10 months agoRenea
11 months agoMertie
11 months agoSteffanie
11 months agoAbel
11 months agoViola
11 months agoYuriko
11 months agoMinna
11 months ago