BCS Exam TM12 Topic 5 Question 110 Discussion

Actual exam question for BCS's TM12 exam
Question #: 110
Topic #: 5
[All TM12 Questions]

You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas.

Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.

Which of the following answers describes the best test execution schedule in this scenario?

Number of correct responses: 1

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Lilli
3 days ago
I think option B is the best choice here. It ensures that each product risk gets at least some testing, while prioritizing the tests based on the risk level.
upvoted 0 times
...