Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 8 Question 73 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 73
Topic #: 8
[All ISEB-PM1 Questions]

A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Krystal
1 days ago
Ah, the classic 'spend more to save time' conundrum. I'm going with B) Schedule compression - the project manager clearly prioritized completing the project early over keeping costs down.
upvoted 0 times
...
Nan
6 days ago
I'm not sure, but I think C) Critical chain could also be a possibility. It focuses on managing project constraints.
upvoted 0 times
...
Kenneth
8 days ago
I agree with Kiley. The project manager traded cost for time, so it makes sense.
upvoted 0 times
...
Kiley
17 days ago
I think the answer is B) Schedule compression.
upvoted 0 times
...

Save Cancel