A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
I'm leaning towards critical chain here. The early completion and increased costs suggest the project manager was focused on the critical path and making tradeoffs to get the project done as quickly as possible.
Hmm, I'm a bit unsure about this one. The increased cost makes me think it could be resource leveling, but the early completion is throwing me off. I'll have to think this through carefully.
This seems like a classic case of schedule compression to me. The project was completed early, but at an increased cost, which is exactly what schedule compression is all about.
Okay, I've got it! This is definitely schedule compression. The project manager traded off increased costs to get the project done faster. Seems like a textbook example.
I'm a bit confused on this one. Is it asking for the command to change the root directory, or the command to run with the changed root directory? I want to make sure I understand the question properly before answering.
Hmm, I'm a bit unsure about this one. I know backup strategies are important, but I'm not totally confident in my knowledge of the best practices. I'll have to think it through carefully.
This is easy, it's B) Schedule compression. Though I'm more impressed by the project manager's ability to make the budget disappear than their time-saving skills.
B) Schedule compression, no doubt. The project manager must be a magician to pull off a $100k cost increase and still finish early. I wonder if they have a rabbit in their hat.
I'm not sure if this is a trick question, but I'm going with B) Schedule compression. Seems like the project manager used some extra resources to get the job done quicker.
Ah, the classic 'spend more to save time' conundrum. I'm going with B) Schedule compression - the project manager clearly prioritized completing the project early over keeping costs down.
Hortencia
10 months agoCorrinne
10 months agoDino
10 months agoVeda
10 months agoAlfred
11 months agoUlysses
11 months agoMinna
11 months agoDominque
11 months agoShawn
11 months agoAudry
11 months agoBrittni
11 months agoAlysa
11 months agoAn
12 months agoWayne
12 months agoShalon
12 months agoStanford
12 months agoTawna
1 year agoCarin
1 year agoDorothea
1 year agoSabra
1 year agoMartina
1 year agoLong
1 year agoMelvin
1 year agoStephaine
1 year agoCatarina
1 year agoSelma
1 year agoBeatriz
1 year agoFelicia
1 year agoKaran
1 year agoClorinda
1 year agoAlise
1 year agoDana
1 year agoDaniela
1 year agoKenneth
1 year agoKrystal
1 year agoSheridan
1 year agoMozell
1 year agoNan
1 year agoKenneth
1 year agoKiley
1 year ago