A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
This is easy, it's B) Schedule compression. Though I'm more impressed by the project manager's ability to make the budget disappear than their time-saving skills.
B) Schedule compression, no doubt. The project manager must be a magician to pull off a $100k cost increase and still finish early. I wonder if they have a rabbit in their hat.
I'm not sure if this is a trick question, but I'm going with B) Schedule compression. Seems like the project manager used some extra resources to get the job done quicker.
Ah, the classic 'spend more to save time' conundrum. I'm going with B) Schedule compression - the project manager clearly prioritized completing the project early over keeping costs down.
Tawna
15 days agoCarin
16 days agoLong
3 days agoMelvin
20 days agoSelma
4 days agoBeatriz
1 months agoFelicia
16 days agoKaran
23 days agoClorinda
27 days agoAlise
27 days agoDana
30 days agoDaniela
1 months agoKenneth
1 months agoKrystal
2 months agoSheridan
29 days agoMozell
1 months agoNan
2 months agoKenneth
2 months agoKiley
2 months ago