A project manager has finished the project. He knows that the project scope has been completed and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:
Ciara
29 days agoBilly
17 days agoKiley
19 days agoSlyvia
20 days agoBette
1 months agoDevora
22 days agoKing
27 days agoMireya
1 months agoWilda
23 days agoElizabeth
1 months agoJade
2 months agoMaile
2 months agoTwila
2 months agoMerri
21 days agoPeggie
23 days agoGlen
2 months ago