Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 1 Question 84 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 84
Topic #: 1
[All ISEB-PM1 Questions]

A project manager has finished the project. He knows that the project scope has been completed and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Ciara
29 days ago
I'm going with B. The project manager did their job, and that's what counts. Now if only my boss could understand that as well as this exam question!
upvoted 0 times
Billy
17 days ago
C) There were so few changes.
upvoted 0 times
...
Kiley
19 days ago
B) It only had six weeks of changes.
upvoted 0 times
...
Slyvia
20 days ago
A) It was completed within the baseline.
upvoted 0 times
...
...
Bette
1 months ago
Hah, this reminds me of that time my boss said my project was a failure because I took an extra week, even though I still finished before the deadline. Bureaucracy, am I right? Anyway, B is the answer here.
upvoted 0 times
Devora
22 days ago
B) It was completed within the baseline.
upvoted 0 times
...
King
27 days ago
A) It only had six weeks of changes.
upvoted 0 times
...
...
Mireya
1 months ago
This is a tricky one, but I think B is the way to go. As long as the project was completed within the baseline, it's a success in my book!
upvoted 0 times
Wilda
23 days ago
User 1: I think B is the correct answer.
upvoted 0 times
...
...
Elizabeth
1 months ago
I agree with B. The project was delivered within the agreed-upon baseline, so it's a success regardless of the original 27-week schedule.
upvoted 0 times
...
Jade
2 months ago
I disagree. Management should focus on the fact that there were so few changes, which shows good project management.
upvoted 0 times
...
Maile
2 months ago
I agree with Glen. As long as it was completed within the baseline, it should be considered a success.
upvoted 0 times
...
Twila
2 months ago
The correct answer is B. The project was completed within the baseline of 33 weeks, so it should be considered a success.
upvoted 0 times
Merri
21 days ago
B: I agree, meeting the baseline is a key factor in determining project success.
upvoted 0 times
...
Peggie
23 days ago
A: Management should consider the project a success since it was completed within the baseline.
upvoted 0 times
...
...
Glen
2 months ago
I think the project is a success because it was completed within the baseline.
upvoted 0 times
...

Save Cancel