Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

BCS Exam ISEB-PM1 Topic 1 Question 84 Discussion

Actual exam question for BCS's ISEB-PM1 exam
Question #: 84
Topic #: 1
[All ISEB-PM1 Questions]

A project manager has finished the project. He knows that the project scope has been completed and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because:

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Maile
2 days ago
I agree with Glen. As long as it was completed within the baseline, it should be considered a success.
upvoted 0 times
...
Twila
6 days ago
The correct answer is B. The project was completed within the baseline of 33 weeks, so it should be considered a success.
upvoted 0 times
...
Glen
10 days ago
I think the project is a success because it was completed within the baseline.
upvoted 0 times
...

Save Cancel