Teams using Project A and B currently use their own respective Scrum boards.
They must now work together on the same products and issues and in the same sprints.
You created a new Scrum board based on this filter:
project in (A,B) ORDER BY Rank ASC
You must also check two settings to make sure the teams can access and use the new board.
Identify the two settings. (Choose two.)
Sharing on the board filter: The board filter must be shared with all users who need access to the board; otherwise, they won't be able to view or use it.
Project permissions: Users must have the necessary permissions (such as Browse Projects and Manage Sprints) on both Project A and Project B to view issues and manage sprints on the new shared board.
Jacinta
5 months agoDino
5 months agoEarlean
5 months agoTyisha
6 months agoNatalie
6 months agoRolland
6 months agoLillian
6 months agoElbert
7 months agoJamal
7 months agoJaime
7 months agoParis
7 months agoTesha
7 months agoCasie
8 months agoNadine
8 months agoEffie
11 months agoPamella
11 months agoRebecka
11 months agoPhillip
11 months agoBuck
10 months agoTegan
10 months agoJoaquin
10 months agoLinette
11 months agoKimi
11 months agoEthan
10 months agoTula
10 months agoJenelle
11 months agoRose
12 months agoNickolas
12 months agoGayla
1 year agoWilda
11 months agoLamar
11 months agoDaniela
12 months agoKristian
1 year agoLorean
1 year agoTomas
11 months agoEvangelina
11 months agoAngella
12 months ago