APMG-International Change-Management-Foundation Exam - Topic 8 Question 63 Discussion

Which of the common Agile concepts, behaviours, and techniques comprises fixed periods of time, at the end of which an objective has been met?
B) Timeboxes (also known as sprints)
A) Minimum viable product
C) Full transparency
D) Focus on frequent delivery

APMG-International Change-Management-Foundation Exam - Topic 8 Question 63 Discussion

Actual exam question for APMG-International's Change-Management-Foundation exam
Question #: 63
Topic #: 8
[All Change-Management-Foundation Questions]

Which of the common Agile concepts, behaviours, and techniques comprises fixed periods of time, at the end of which an objective has been met?

Show Suggested Answer Hide Answer
Suggested Answer: B

Comprehensive and Detailed In-Depth

In Agile methodology, as covered in the APMG Change Management Foundation, Timeboxes (Option B), also known as sprints in Scrum, are fixed time periods (e.g., 2--4 weeks) during which specific objectives or deliverables are completed. This structured approach ensures focus and progress. Minimum viable product (A) refers to a basic product version, Full transparency (C) to open communication, and Focus on frequent delivery (D) to regular outputs---none inherently involve fixed time periods with completed objectives like Timeboxes.


Contribute your Thoughts:

0/2000 characters
Shanda
1 day ago
Definitely B) Timeboxes, that's a core Agile principle.
upvoted 0 times
...
Fairy
7 days ago
I recall that timeboxes are crucial for Agile, especially in Scrum, so I’m leaning towards B as the correct answer.
upvoted 0 times
...
Ligia
12 days ago
I’m a bit confused because I thought Minimum Viable Product also had a time aspect, but I guess it’s more about the product itself, not the time period.
upvoted 0 times
...
Marion
17 days ago
I remember practicing a question about sprints and their role in Agile, so I feel like B is definitely the right choice here.
upvoted 0 times
...
Dino
22 days ago
I think the answer might be B) Timeboxes, but I'm not entirely sure if that's the only term used for fixed periods in Agile.
upvoted 0 times
...