APMG-International AgilePM-Practitioner Exam - Topic 3 Question 21 Discussion

Which 2 actions should the Workshop Facilitator take to implement the newMust Have requirement?
B) Consolidate and circulate an agenda for the workshop. and E) Encourage all parties to contribute, irrespective of their views.
A) Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
C) Send a company-wide communication to explain the implications of the business change to all interested parties.
D) Assess the impact of the additional development costs on the original Business Case.

APMG-International AgilePM-Practitioner Exam - Topic 3 Question 21 Discussion

Actual exam question for APMG-International's AgilePM-Practitioner exam
Question #: 21
Topic #: 3
[All AgilePM-Practitioner Questions]

Which 2 actions should the Workshop Facilitator take to implement the new

Must Have requirement?

Show Suggested Answer Hide Answer
Suggested Answer: B, E

Contribute your Thoughts:

0/2000 characters
Alpha
6 months ago
I agree, everyone should contribute their thoughts!
upvoted 0 times
...
Nieves
6 months ago
Wait, are we really assessing the impact on the Business Case? That seems intense!
upvoted 0 times
...
Johnetta
7 months ago
Not sure if sending a company-wide communication is necessary.
upvoted 0 times
...
Merlyn
7 months ago
I think circulating an agenda is super important too.
upvoted 0 times
...
Lang
7 months ago
Definitely need to add tasks to the Delivery Plan!
upvoted 0 times
...
Barrett
7 months ago
I recall a practice question where assessing impact was key, so D might be relevant here as well. It’s tough to choose!
upvoted 0 times
...
Mari
7 months ago
I feel like option C could be important too, especially if it involves communicating changes to everyone. But I’m not 100% certain.
upvoted 0 times
...
Marisha
8 months ago
I'm not entirely sure, but I remember something about circulating an agenda being crucial for workshops. Maybe B is a good choice?
upvoted 0 times
...
Diego
8 months ago
I think we talked about the importance of adding tasks to the Delivery Plan, so option A might be one of the right answers.
upvoted 0 times
...
Gerry
8 months ago
I'm leaning towards A and E. Adding the tasks to the Delivery Plan is a given, and encouraging broad participation in the workshop will help ensure we get the right input to make this work. The other choices don't seem as critical.
upvoted 0 times
...
Janet
8 months ago
Okay, let's see. I think A and D make the most sense - we need to update the Delivery Plan and also assess the impact on the Business Case. The other options don't seem as directly relevant to implementing the new requirement.
upvoted 0 times
...
Brendan
8 months ago
Hmm, I'm a bit unsure about this one. There are a few options that seem relevant, but I'm not totally confident which two are the best approach. I'll have to think it through carefully.
upvoted 0 times
...
Oliva
8 months ago
This seems straightforward - I'd go with A and B to implement the new requirement. Adding the tasks to the Delivery Plan and consolidating the workshop agenda are the logical next steps.
upvoted 0 times
...
Stevie
1 year ago
I'd add a touch of humor and suggest the facilitator bring donuts to keep the stakeholders happy and engaged.
upvoted 0 times
Rueben
1 year ago
E) Encourage all parties to contribute, irrespective of their views.
upvoted 0 times
...
Iesha
1 year ago
C) Send a company-wide communication to explain the implications of the business change to all interested parties.
upvoted 0 times
...
Tawna
1 year ago
B) Consolidate and circulate an agenda for the workshop.
upvoted 0 times
...
Sharmaine
1 year ago
A) Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
upvoted 0 times
...
...
Elvera
1 year ago
I believe sending a company-wide communication is also crucial to keep everyone informed.
upvoted 0 times
...
Georgeanna
1 year ago
B and C are important too. Getting everyone on the same page is crucial.
upvoted 0 times
...
Lucy
1 year ago
E is a must! Encouraging participation is key to a successful workshop.
upvoted 0 times
Man
1 year ago
B) Consolidate and circulate an agenda for the workshop.
upvoted 0 times
...
Augustine
1 year ago
E) Encourage all parties to contribute, irrespective of their views.
upvoted 0 times
...
Tyisha
1 year ago
E) Encourage all parties to contribute, irrespective of their views.
upvoted 0 times
...
Arlen
1 year ago
A) Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
upvoted 0 times
...
Rose
1 year ago
A) Add the tasks required to develop the new financial transaction functionality to the Delivery Plan.
upvoted 0 times
...
...
Lenna
1 year ago
I agree with Artie. It's important to have a clear plan in place.
upvoted 0 times
...
Artie
1 year ago
I think the Workshop Facilitator should add the tasks to the Delivery Plan.
upvoted 0 times
...
Rolande
1 year ago
A and D for sure. The new requirement needs to be factored into the delivery plan and the business case.
upvoted 0 times
Paz
1 year ago
User 4: Communication and collaboration are also important, so E should not be overlooked.
upvoted 0 times
...
Arlette
1 year ago
User 3: It's important to have a clear plan and understand the financial implications before moving forward.
upvoted 0 times
...
Caprice
1 year ago
User 2: I agree, adding the tasks to the delivery plan and assessing the impact on the business case are key steps.
upvoted 0 times
...
Hector
1 year ago
User 1: A and D are crucial to ensure the new requirement is properly integrated.
upvoted 0 times
...
...