APMG-International AgilePM Foundation Exam - Topic 1 Question 69 Discussion

Which should always be the first step in the Continuous Change Management Cycle?
C) Discovery.
A) Ideas.
B) Prioritization.
D) Action.

APMG-International AgilePM Foundation Exam - Topic 1 Question 69 Discussion

Actual exam question for APMG-International's AgilePM Foundation exam
Question #: 69
Topic #: 1
[All AgilePM Foundation Questions]

Which should always be the first step in the Continuous Change Management Cycle?

Show Suggested Answer Hide Answer
Suggested Answer: C

Discovery: The Continuous Change Management Cycle starts with understanding the current situation, challenges, and opportunities. Discovery ensures that subsequent steps are informed and targeted.

Other Options:

A: Ideas come after discovery.

B: Prioritization occurs after potential solutions are identified.

D: Action follows the planning and prioritization phases.

Key AgilePM Concepts Referenced:

Continuous Change Management Cycle: AgilePM Handbook, Chapter 6, Section 6.6.