APMG-International Exam AgilePM-Foundation Topic 1 Question 29 Discussion

Actual exam question for APMG-International's AgilePM-Foundation exam
Question #: 29
Topic #: 1
[All AgilePM-Foundation Questions]

Which of the following statements about a communication plan are true?

Same overall format for all change initiatives.

Content will differ depending on the scale and complexity of change.

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Javier
20 days ago
Hmm, I'll go with C as well. Although, I do wonder if the communication plan should also have a bit of humor sprinkled in, just to keep things interesting. Maybe a few memes or dad jokes here and there.
upvoted 0 times
...
Lorita
23 days ago
Definitely C. If the communication plan was exactly the same for every change, it wouldn't be very effective. Gotta adapt it to the situation.
upvoted 0 times
...
Xenia
1 months ago
I agree, C is the right answer. The communication plan needs to be tailored to the specific change initiative, but there should be a standard structure that applies across the board.
upvoted 0 times
Fallon
4 days ago
C) Both 1 and 2 are true.
upvoted 0 times
...
Reuben
15 days ago
B) Only 2 is true.
upvoted 0 times
...
Susy
16 days ago
A) Only 1 is true.
upvoted 0 times
...
...
Chau
1 months ago
I think the correct answer is C. Both statements seem to be true - the communication plan will have a consistent overall format, but the content will vary depending on the scale and complexity of the change.
upvoted 0 times
...
Denae
2 months ago
I'm not sure, but I think the answer might be B.
upvoted 0 times
...
Maile
2 months ago
I agree with Felicia, because the content should vary based on the change complexity.
upvoted 0 times
...
Felicia
2 months ago
I think the answer is C.
upvoted 0 times
...