Question #: 12
Topic #: 7
[All AgileBA-Foundation Questions]

Who is responsible for estimating within a DSDM project?

Show Suggested Answer Hide Answer
Suggested Answer: C

Within a DSDM (Dynamic Systems Development Method) project, the Solution Development Team is responsible for estimating. This team includes developers, testers, and business representatives who collaboratively estimate the effort required for each requirement. Their combined expertise ensures that the estimates are realistic and achievable, facilitating effective planning and delivery of the project.

Reference: Business Analysis.pdf, Chapter 11, Documenting and Managing Requirements


Contribute your Thoughts:

Joseph
10 months ago
I see your point, Elliot. The Solution Development Team would have a better grasp of the technical aspects for accurate estimation.
upvoted 0 times
...
Alecia
11 months ago
Business Advisor? I guess they could estimate how much coffee the team will need to survive the project, but that's about it.
upvoted 0 times
...
Annamae
11 months ago
Planning specialist? Really? Isn't that just a fancy term for someone with a crystal ball and a magic wand?
upvoted 0 times
Jeanice
9 months ago
C) Solution Development Team
upvoted 0 times
...
Ocie
9 months ago
True, they do have to work some magic sometimes!
upvoted 0 times
...
Jonelle
9 months ago
B) Project Manager
upvoted 0 times
...
Malcolm
9 months ago
Haha, I guess you could say that!
upvoted 0 times
...
Lawanda
9 months ago
D) Planning specialist
upvoted 0 times
...
Mariann
10 months ago
C) Solution Development Team
upvoted 0 times
...
Jolene
10 months ago
B) Project Manager
upvoted 0 times
...
Alayna
10 months ago
A) Business Advisor
upvoted 0 times
...
...
Elliot
11 months ago
Actually, I believe it's the Solution Development Team because they are the ones working closely on the project deliverables.
upvoted 0 times
...
Earleen
11 months ago
I agree with Gilma, the Project Manager should have a good understanding of the project scope.
upvoted 0 times
...
Gilma
11 months ago
I think the Project Manager is responsible for estimating.
upvoted 0 times
...
Talia
11 months ago
I'd go with the Solution Development Team on this one. They're the ones who know the nitty-gritty details and can provide the most accurate estimates.
upvoted 0 times
...
Chuck
11 months ago
The Project Manager is responsible for estimating in a DSDM project. They have the big picture and can coordinate the team's efforts.
upvoted 0 times
Marylin
11 months ago
C) Solution Development Team
upvoted 0 times
...
Reena
11 months ago
That makes sense, the Project Manager is responsible for estimating in a DSDM project.
upvoted 0 times
...
Leanna
11 months ago
B) Project Manager
upvoted 0 times
...
...