During which process phase is the Prioritised Requirements List baselined?

Show Suggested Answer Hide Answer
Suggested Answer: B

The Prioritised Requirements List (PRL) is baselined during the Foundations phase. This phase is critical for establishing a clear understanding of the requirements and priorities before the development work begins. Baselining the PRL ensures that there is a formal agreement on the scope and priorities of the requirements, which serves as a foundation for subsequent development iterations.


Business Analysis.pdf, 'requirements validation is carried out to review and agree the requirements documentation...At this point the CIs that describe the requirements are said to be 'baselined''.

Contribute your Thoughts:

0/2000 characters
Lauran
3 months ago
Foundations makes sense, but I’m still a bit confused.
upvoted 0 times
...
Stephane
3 months ago
I thought it was part of Evolutionary Development?
upvoted 0 times
...
Alberto
3 months ago
Wait, are you sure it's not during Deployment?
upvoted 0 times
...
Carma
4 months ago
Totally agree, Foundations is key for that!
upvoted 0 times
...
Milly
4 months ago
It's baselined during the Foundations phase.
upvoted 0 times
...
Micah
4 months ago
Deployment seems too late for baselining requirements, right? Foundations feels more appropriate.
upvoted 0 times
...
Floyd
4 months ago
I’m leaning towards Evolutionary Development, but I can't recall the specifics.
upvoted 0 times
...
Ilene
4 months ago
I remember practicing a question about this, and I feel like it might be during the Feasibility phase instead.
upvoted 0 times
...
Luke
5 months ago
I think the Prioritised Requirements List is baselined during the Foundations phase, but I'm not entirely sure.
upvoted 0 times
...
Mari
5 months ago
I'm pretty confident I know the answer to this one. The Prioritised Requirements List is definitely baselined during the Foundations phase.
upvoted 0 times
...
Avery
5 months ago
Hmm, I'm a bit confused on this one. I'll have to review my notes to see where the Prioritised Requirements List is discussed.
upvoted 0 times
...
Justine
5 months ago
This one seems tricky, but I think I can figure it out if I think it through step-by-step.
upvoted 0 times
...
Shoshana
5 months ago
Okay, I've got a strategy for this. I'll eliminate the options that don't seem relevant, then focus in on the most likely answer.
upvoted 0 times
...
Lizbeth
5 months ago
I'm pretty confident the answer is Synchronized Data Sources. That's the feature designed for connecting data across Salesforce products, so it makes the most sense for this scenario.
upvoted 0 times
...
Lindy
1 year ago
Wow, they really want to trip us up with this one, huh? Time to put on my thinking cap and make a wild guess. I'll go with C) Evolutionary Development, just for fun.
upvoted 0 times
...
Joseph
1 year ago
I'm going with B) Foundations. It just makes the most sense to me as the phase where the requirements are solidified and approved.
upvoted 0 times
Loreta
1 year ago
I'm not sure, but I'll go with B) Foundations too. It does make sense for the requirements to be finalised at that stage.
upvoted 0 times
...
Page
1 year ago
I think it could also be C) Evolutionary Development, as requirements may evolve during this phase.
upvoted 0 times
...
Jerry
1 year ago
I agree, B) Foundations seems like the right choice for baselining the requirements.
upvoted 0 times
...
...
Alexia
1 year ago
A) Feasibility? Nah, that's too early in the process. The requirements need to be fleshed out first before they can be baselined.
upvoted 0 times
...
Brice
1 year ago
D) Deployment? Really? I don't think that's when the requirements get baselined. Seems more like the final phase to me.
upvoted 0 times
...
Dean
1 year ago
Hmm, I'm not so sure. Could it be C) Evolutionary Development? I know that's where the requirements are continuously refined and updated.
upvoted 0 times
Nu
1 year ago
User 3: I'm not sure, but it does sound like the right phase to do it.
upvoted 0 times
...
Caitlin
1 year ago
Yeah, I agree. It makes sense to baseline the Prioritised Requirements List during Evolutionary Development.
upvoted 0 times
...
Yuonne
1 year ago
I think you might be right. That's when the requirements are finalized.
upvoted 0 times
...
...
Reuben
1 year ago
I think it's B) Foundations. That's where the requirements are defined and baselined, right?
upvoted 0 times
Lon
1 year ago
D) Deployment
upvoted 0 times
...
Marlon
1 year ago
C) Evolutionary Development
upvoted 0 times
...
Tracey
1 year ago
B) Foundations
upvoted 0 times
...
Alline
1 year ago
A) Feasibility
upvoted 0 times
...
...
Berry
1 year ago
Hmm, that makes sense too. It's important to have a solid foundation before evolving the requirements.
upvoted 0 times
...
Wei
1 year ago
I disagree, I believe it happens during Evolutionary Development.
upvoted 0 times
...
Berry
1 year ago
I think the Prioritised Requirements List is baselined during Foundations.
upvoted 0 times
...

Save Cancel