Aside from predecessors, resource manager assignments, and system administrator settings, what are three prerequisites for using the Resource Planner and Workload Balancer? (Choose three.)
Objective: Identify prerequisites for using the Resource Planner and Workload Balancer.
Prerequisites:
Prerequisite 1: Job Roles assigned to Tasks
Prerequisite 2: Task Planned Hours greater than zero
Prerequisite 3: Task Durations greater than zero