Refer to the exhibit.

Tyson has a capacity of 7 hours per day.
What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)
To ensure Tyson is not over-allocated in the Workload Balancer, a system administrator can take the following actions:
Edit Task Allocation: The administrator can adjust the allocation of hours for the 'Verify Intake Form' task. Specifically, they can redistribute the hours from Wednesday (where Tyson is over-allocated with 9 hours) to other days where Tyson has available capacity.
Reassign Task: The administrator can reassign the 'Kickoff Meeting' task to another user who has available capacity. This will immediately reduce Tyson's workload and ensure the task is still completed without overburdening Tyson.
Reference
Workfront documentation on using the Workload Balancer highlights these options for managing user allocations and ensuring workloads are balanced across team members.
Bulah
4 months agoAntonio
4 months agoAdelina
4 months agoNidia
4 months agoMickie
4 months agoEmilio
5 months agoVon
5 months agoZack
5 months agoMarsha
5 months agoBrittni
6 months agoLeslee
6 months agoArleen
6 months agoJacinta
6 months agoJani
6 months agoJovita
11 months agoRaymon
11 months agoShawn
10 months agoHildred
10 months agoHelaine
10 months agoFelicia
11 months agoDarrin
10 months agoTu
10 months agoLeah
10 months agoEzekiel
11 months agoGilma
12 months agoSanjuana
10 months agoSkye
11 months agoBarrett
11 months agoCarman
11 months agoShawnee
12 months agoMozell
12 months agoTamekia
1 year agoRuth
10 months agoCaitlin
11 months agoAleta
11 months agoBok
11 months agoShonda
11 months ago