Refer to the exhibit.

Tyson has a capacity of 7 hours per day.
What two changes can the system administrator make to this user's workload from within the Workload Balancer to ensure that they are not overallocated? (Choose two.)
To ensure Tyson is not over-allocated in the Workload Balancer, a system administrator can take the following actions:
Edit Task Allocation: The administrator can adjust the allocation of hours for the 'Verify Intake Form' task. Specifically, they can redistribute the hours from Wednesday (where Tyson is over-allocated with 9 hours) to other days where Tyson has available capacity.
Reassign Task: The administrator can reassign the 'Kickoff Meeting' task to another user who has available capacity. This will immediately reduce Tyson's workload and ensure the task is still completed without overburdening Tyson.
Reference
Workfront documentation on using the Workload Balancer highlights these options for managing user allocations and ensuring workloads are balanced across team members.
Bulah
2 months agoAntonio
2 months agoAdelina
2 months agoNidia
3 months agoMickie
3 months agoEmilio
3 months agoVon
3 months agoZack
4 months agoMarsha
4 months agoBrittni
4 months agoLeslee
4 months agoArleen
4 months agoJacinta
5 months agoJani
5 months agoJovita
9 months agoRaymon
9 months agoShawn
8 months agoHildred
9 months agoHelaine
9 months agoFelicia
10 months agoDarrin
9 months agoTu
9 months agoLeah
9 months agoEzekiel
10 months agoGilma
10 months agoSanjuana
9 months agoSkye
10 months agoBarrett
10 months agoCarman
10 months agoShawnee
10 months agoMozell
10 months agoTamekia
11 months agoRuth
9 months agoCaitlin
9 months agoAleta
9 months agoBok
9 months agoShonda
10 months ago