Adobe AD0-E903 Exam - Topic 3 Question 33 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 33
Topic #: 3
[All AD0-E903 Questions]

Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

Show Suggested Answer Hide Answer
Suggested Answer: B

In Adobe Workfront, to avoid sending unnecessary notifications when adjusting timelines, the Recalculate the project timeline option is used. This ensures that the timeline is updated appropriately based on the changes, but it prevents the system from sending notification alerts to the project team. Recalculation helps align task dependencies and timeline adjustments, preventing confusion among team members.


Contribute your Thoughts:

0/2000 characters

Currently there are no comments in this discussion, be the first to comment!


Save Cancel