New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Adobe AD0-E903 Exam - Topic 3 Question 10 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 10
Topic #: 3
[All AD0-E903 Questions]

Given this information regarding a Task:

* Planned Start Date: May 14

* Actual Start Date: May 14

* Planned Completion Date: May 20

* Projected Completion Date: May 22

* Percent Complete: 50%

* Duration: 5 Days

* Planned Hours: 8 Hours

* Status: In Progress

If today's date were May 19, what would be the Task's progress status?

Show Suggested Answer Hide Answer
Suggested Answer: C

In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.


Contribute your Thoughts:

0/2000 characters
Dominga
3 months ago
Seems like they underestimated the time needed.
upvoted 0 times
...
Jamal
3 months ago
Wait, how can it be 50% complete with two days left?
upvoted 0 times
...
Mindy
3 months ago
I think it's at risk, not behind.
upvoted 0 times
...
Lindsay
4 months ago
Definitely behind schedule!
upvoted 0 times
...
Chuck
4 months ago
It's only 50% done with one day left.
upvoted 0 times
...
Denae
4 months ago
I wonder if "on time" could apply here since the actual start date matches the planned one, but the projected completion date throws me off.
upvoted 0 times
...
Elliott
4 months ago
I practiced a similar question, and I feel like if we're only at 50% by May 19, that might mean we're behind.
upvoted 0 times
...
Fannie
4 months ago
I'm not entirely sure, but I remember something about being at risk if the percent complete is less than expected by the due date.
upvoted 0 times
...
Launa
5 months ago
I think the task is behind schedule since the projected completion date is later than planned.
upvoted 0 times
...
Stanford
5 months ago
This is a good example of a task progress question. I'll start by calculating the planned duration and then compare the actual progress to the planned timeline to determine the status.
upvoted 0 times
...
Sylvie
5 months ago
Okay, I've got this. The task was planned for 5 days, and it's 50% complete on May 19, so it's behind schedule. The answer must be A, "Behind".
upvoted 0 times
...
Eloisa
5 months ago
Hmm, let me think this through. The task started on May 14 and was planned to be completed by May 20, but it's now May 19 and it's only 50% complete. I'll need to do some calculations to determine the status.
upvoted 0 times
...
Paris
5 months ago
This looks like a straightforward task progress question. I'll start by calculating the planned duration and compare it to the projected completion date.
upvoted 0 times
...
Gerald
5 months ago
I'm a bit confused on how to approach this. The information seems straightforward, but I want to make sure I'm not missing anything. I'll double-check my work to be sure.
upvoted 0 times
...
Maybelle
1 year ago
I'm just glad the task isn't status 'Abandoned' or 'Terminated'. Now that would be a real problem!
upvoted 0 times
...
Willard
1 year ago
This is a no-brainer. If a task is only 50% done with one day left in the planned schedule, it's definitely A) Behind. Someone needs to get their act together on this project!
upvoted 0 times
Anthony
1 year ago
A) Behind
upvoted 0 times
...
Maia
1 year ago
A) Behind
upvoted 0 times
...
Taryn
1 year ago
A) Behind
upvoted 0 times
...
...
Gene
1 year ago
With the task only 50% complete on May 19, and the planned completion date being May 20, I'd say B) On Time is the correct answer. The task is still on schedule, even if it's projected to finish a couple days late.
upvoted 0 times
Lina
1 year ago
C) At Risk
upvoted 0 times
...
Dean
1 year ago
B) On Time
upvoted 0 times
...
Denae
1 year ago
A) Behind
upvoted 0 times
...
...
Floyd
1 year ago
C) At Risk seems like the right answer here. The task is projected to be completed on May 22, which is after the planned completion date of May 20, so it's at risk of being delayed.
upvoted 0 times
Judy
1 year ago
C) At Risk seems like the right answer here. The task is projected to be completed on May 22, which is after the planned completion date of May 20, so it's at risk of being delayed.
upvoted 0 times
...
Jeannetta
1 year ago
C) At Risk
upvoted 0 times
...
Refugia
1 year ago
B) On Time
upvoted 0 times
...
Marleen
1 year ago
A) Behind
upvoted 0 times
...
...
Beckie
1 year ago
I think the task is at risk because even though it's not yet past the planned completion date, the progress is only at 50%.
upvoted 0 times
...
Yong
1 year ago
I agree with Eva, the task is behind because the projected completion date is after the planned completion date.
upvoted 0 times
...
Coral
1 year ago
If the task is only 50% complete on May 19, but the planned completion date is May 20, then it's definitely behind schedule. The answer has to be A) Behind.
upvoted 0 times
Murray
1 year ago
Let's make sure to adjust the timeline for future tasks to avoid delays.
upvoted 0 times
...
Irma
1 year ago
It's important to keep track of progress to avoid falling behind.
upvoted 0 times
...
France
1 year ago
I agree, the task is definitely behind schedule.
upvoted 0 times
...
Cathrine
1 year ago
A) Behind
upvoted 0 times
...
Dominga
1 year ago
A) Behind
upvoted 0 times
...
...
Eva
1 year ago
I think the task is behind schedule.
upvoted 0 times
...

Save Cancel