Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.
Dominga
10 months agoJamal
10 months agoMindy
10 months agoLindsay
10 months agoChuck
10 months agoDenae
11 months agoElliott
11 months agoFannie
11 months agoLauna
11 months agoStanford
11 months agoSylvie
11 months agoEloisa
11 months agoParis
11 months agoGerald
11 months agoMaybelle
2 years agoWillard
2 years agoAnthony
2 years agoMaia
2 years agoTaryn
2 years agoGene
2 years agoLina
2 years agoDean
2 years agoDenae
2 years agoFloyd
2 years agoJudy
2 years agoJeannetta
2 years agoRefugia
2 years agoMarleen
2 years agoBeckie
2 years agoYong
2 years agoCoral
2 years agoMurray
2 years agoIrma
2 years agoFrance
2 years agoCathrine
2 years agoDominga
2 years agoEva
2 years ago