Given this information regarding a Task:
* Planned Start Date: May 14
* Actual Start Date: May 14
* Planned Completion Date: May 20
* Projected Completion Date: May 22
* Percent Complete: 50%
* Duration: 5 Days
* Planned Hours: 8 Hours
* Status: In Progress
If today's date were May 19, what would be the Task's progress status?
In Workfront, when the projected completion date exceeds the planned completion date and the task is only 50% complete by May 19, it is automatically flagged as 'At Risk.' This alerts the project manager that the task is not progressing according to the original plan, potentially causing delays in the project timeline.
Maybelle
10 months agoWillard
10 months agoAnthony
9 months agoMaia
9 months agoTaryn
9 months agoGene
10 months agoLina
9 months agoDean
9 months agoDenae
9 months agoFloyd
10 months agoJudy
9 months agoJeannetta
9 months agoRefugia
9 months agoMarleen
9 months agoBeckie
10 months agoYong
10 months agoCoral
11 months agoMurray
9 months agoIrma
9 months agoFrance
9 months agoCathrine
10 months agoDominga
10 months agoEva
11 months ago