A client has negotiated a discounted billing rate for video editing in a specific initiative.
How can the project manager override the default billing rate for the Video Editor within a project?
In Workfront, billing rates can be customized for individual projects. To apply a negotiated rate for the Video Editor role within a specific initiative, the project manager can add a new billing rate at the project level. This ensures that the rate is applied only to tasks within the project and does not affect the default system-wide rate for other projects.