Adobe AD0-E903 Exam - Topic 2 Question 28 Discussion

Actual exam question for Adobe's AD0-E903 exam
Question #: 28
Topic #: 2
[All AD0-E903 Questions]

A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.

What task setting needs to change to allow 4 users to complete this in less than 3 days?

Show Suggested Answer Hide Answer
Suggested Answer: B

When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to 'Calculated Work' allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.


Contribute your Thoughts:

0/2000 characters
Chauncey
1 day ago
Isn't that too tight of a deadline?
upvoted 0 times
...
Jerrod
6 days ago
I think changing to Effort Driven makes sense!
upvoted 0 times
...
Fatima
12 days ago
Just need to increase the team size to 4.
upvoted 0 times
...
Arminda
17 days ago
Wait, we're supposed to do work? I thought this was a nap exam.
upvoted 0 times
...
Tawna
22 days ago
Hmm, I'd just use a time machine to finish this in 1 day. Problem solved!
upvoted 0 times
...
Annelle
27 days ago
D) Change the Task Constraint to As Soon As Possible. Gotta get this done ASAP, no time to waste!
upvoted 0 times
...
Corinne
1 month ago
A) Change the Task Duration Type to Effort Driven. This will allow more resources to be added to complete the task faster.
upvoted 0 times
...
Leanora
1 month ago
I practiced a similar question about task durations, and I think effort-driven might be the right choice, but I need to double-check the definitions.
upvoted 0 times
...
Alida
1 month ago
I feel like changing the task constraint to fixed dates could help, but it seems risky if we can't meet the deadline.
upvoted 0 times
...
Odette
2 months ago
Changing the Task Constraint to As Soon As Possible could be the quickest solution, but I'm not 100% sure.
upvoted 0 times
...
Erinn
2 months ago
I'm leaning towards option B, but I want to double-check the details on how that would impact the timeline.
upvoted 0 times
...
Glendora
2 months ago
Okay, let me see. I think changing the Task Duration Type to Calculated Work might be the way to go here.
upvoted 0 times
...
Donte
2 months ago
I think we might need to change the task duration type to effort-driven, but I'm not entirely sure how that affects the overall timeline.
upvoted 0 times
...
Peter
2 months ago
B) Change the Task Duration Type to Calculated Work. This will adjust the duration based on the work and resources.
upvoted 0 times
...
Tom
3 months ago
I remember a practice question where we had to adjust constraints, but I can't recall if fixed dates or as soon as possible is better for this scenario.
upvoted 0 times
...
Ammie
3 months ago
C) Change the Task Constraint to Fixed Dates. Deadlines are deadlines, no exceptions!
upvoted 0 times
...
Francesco
3 months ago
Hmm, I'm a bit confused. I'm not sure which setting would be the best to change to get this done in less than 3 days.
upvoted 0 times
...
Bobbie
3 months ago
This seems like a tricky one. I'd need to think through the different options carefully.
upvoted 0 times
Ashleigh
2 months ago
This is definitely tricky! I think we need to consider the effort involved.
upvoted 0 times
...
...