A task was originally planned with a 10-day duration and 40 planned hours. The client needs it done in 3 days.
What task setting needs to change to allow 4 users to complete this in less than 3 days?
When reducing the task duration and distributing the work among multiple users, changing the Task Duration Type to 'Calculated Work' allows Workfront to automatically adjust the duration based on the number of assignees (in this case, 4 users). This will enable the task to be completed within the new shorter timeframe without adjusting the total planned hours.
Chauncey
1 day agoJerrod
6 days agoFatima
12 days agoArminda
17 days agoTawna
22 days agoAnnelle
27 days agoCorinne
1 month agoLeanora
1 month agoAlida
1 month agoOdette
2 months agoErinn
2 months agoGlendora
2 months agoDonte
2 months agoPeter
2 months agoTom
3 months agoAmmie
3 months agoFrancesco
3 months agoBobbie
3 months agoAshleigh
2 months ago