A project manager is assigned to a new Workfront request. The request specifies that the management team's sign-off is needed before the project can begin.
What is the appropriate action for the project manager to take?
In Workfront, approval processes are designed to handle scenarios where certain team members must give formal approval before work can proceed. In this case, the project manager should set up a customized approval process that routes the request through the necessary stakeholders (management team) for their sign-off. This ensures proper governance and tracking.