Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 4 Question 44 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 44
Topic #: 4
[All AACE-PSP Questions]

The amount of time that an activity can be delayed from its early start date without delaying project completion is called:

Show Suggested Answer Hide Answer
Suggested Answer: C

The time an activity can be delayed from its early start without impacting the overall project completion date is called total float.

Option A (negative float) refers to delays beyond permissible limits.

Option B (free float) refers to delays without affecting the early start of any successor.

Option D (interfering float) is a lesser-used term denoting the time available without delaying the project completion but affecting a successor's float.


Contribute your Thoughts:

0/2000 characters
Irma
5 days ago
I feel confused. What’s the difference between free and total float?
upvoted 0 times
...
Janna
10 days ago
C) Total float is definitely the best answer. It’s all about managing time.
upvoted 0 times
...
Shanda
16 days ago
No, I believe it’s C) Total float. It’s crucial for project completion.
upvoted 0 times
...
Ma
21 days ago
I’m leaning towards B) Free float. It’s about individual tasks, right?
upvoted 0 times
...
Geoffrey
26 days ago
I agree, C) Total float is the right choice. It covers overall delays.
upvoted 0 times
...
Josephine
1 month ago
I think it's C) Total float. It makes sense for project timing.
upvoted 0 times
...
Val
1 month ago
I agree, Total float is the right answer!
upvoted 0 times
...
Paz
1 month ago
Wait, is there really a term like Interfering float?
upvoted 0 times
...
Willodean
2 months ago
Definitely Total float, no doubt!
upvoted 0 times
...
Shasta
2 months ago
I thought it was Free float.
upvoted 0 times
...
Horace
2 months ago
It's called Total float!
upvoted 0 times
...
Georgiana
3 months ago
B) Free float. Gotta love those floats, am I right?
upvoted 0 times
...
Margot
3 months ago
C) Total float. Duh, everyone knows that!
upvoted 0 times
...
Reita
3 months ago
D) Interfering float. Sounds like a made-up term to me.
upvoted 0 times
...
Fletcher
3 months ago
C) Total float. Makes the most sense to me.
upvoted 0 times
...
Jeannetta
3 months ago
A) Negative float. Hmm, not sure about that one.
upvoted 0 times
...
Isadora
3 months ago
B) Free float. Definitely the right choice here.
upvoted 0 times
...
Kimi
4 months ago
C) Total float. This is the correct answer.
upvoted 0 times
...
Twanna
4 months ago
I’m really unsure about this one. Negative float sounds familiar, but I don’t think it fits the definition given.
upvoted 0 times
...
Jesusita
4 months ago
I feel like I’ve seen a question like this before, and I think the answer was total float, but I could be mixing it up with free float.
upvoted 0 times
...
Tyra
4 months ago
I remember something about total float being the overall delay possible without affecting the project end date.
upvoted 0 times
...
Jesus
4 months ago
I think it's either free float or total float, but I'm not entirely sure which one applies here.
upvoted 0 times
...
Erick
4 months ago
I'm pretty confident the answer is C) Total float. That's the key project management concept that describes the flexibility in an activity's schedule before it impacts the overall project timeline.
upvoted 0 times
...
Luis
5 months ago
Okay, let me reason this through. The question is asking about the amount of time an activity can be delayed without delaying the project. That sounds like the definition of total float to me, so I'll go with C) Total float.
upvoted 0 times
...
Xenia
6 months ago
Hmm, I'm a bit unsure about this one. Is it B) Free float or C) Total float? I'll need to think through the definitions of those terms carefully.
upvoted 0 times
...
Delfina
6 months ago
I think the answer is C) Total float. That sounds like the right concept to describe the amount of time an activity can be delayed without impacting the project end date.
upvoted 0 times
Deeann
2 hours ago
C) Total float is definitely the right choice.
upvoted 0 times
...
Abel
5 months ago
I thought it was B) Free float at first.
upvoted 0 times
...
Thaddeus
5 months ago
I agree, C) Total float makes sense.
upvoted 0 times
...
Emeline
5 months ago
I’m with you all, C) Total float is the way to go!
upvoted 0 times
...
Leontine
5 months ago
Yeah, it fits the definition perfectly!
upvoted 0 times
...
...

Save Cancel