Each of the following accurately describes total float in a schedule EXCEPT:
Suggested Answer: C
Get Premium AACE-PSP Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
Total float measures the flexibility in an activity's timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project's overall completion date or the completion date of any of its successors.
Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
Option C describes free float, not total float, and thus is incorrect.
29 comments · newest first
AL
Alexis
7 months ago
I’m leaning towards B too. Total float should always be non-negative.
PE
Peter
8 months ago
I think D is straightforward. It’s all about early and late finishes.
GE
Gennie
8 months ago
Right! A, C, and D all sound correct to me.
GO
Goldie
8 months ago
Yes, B doesn't make sense. Float can't be negative.
ME
Melynda
9 months ago
I agree! I feel like B is the odd one out.
MA
Magnolia
9 months ago
D is correct; that’s how you calculate float!
GL
Glynda
9 months ago
C is misleading; it’s not just about other activities.
KA
Kanisha
9 months ago
Wait, can float really be negative? That sounds weird.
AV
Avery
9 months ago
I agree, A is spot on!
CO
Corinne
9 months ago
Option B is the funniest answer. Total float can be positive or negative, just like my mood during exams.
KA
Kattie
10 months ago
Option A is wrong. Total float is the amount of time an activity can be delayed without delaying the project completion.
MA
Matthew
10 months ago
Option C is the best description of total float. It's the amount of time an activity can be delayed without affecting other activities.
DE
Denny
10 months ago
Option D is the correct answer. Total float is computed by subtracting early finish from late finish or early start from late start.
EL
Elbert
10 months ago
Option B is correct. Total float can be positive or negative.
SI
Silva
10 months ago
Total float - that's a concept I struggled with a bit in class. I'll need to review my notes and make sure I fully understand it before attempting this.
LE
Levi
10 months ago
Total float is definitely the time an activity can be delayed without affecting the project.
TH
Thersa
11 months ago
I think the question is tricky. Total float can be confusing.
AN
An
11 months ago
This is a classic project management question. I'm pretty confident I can work through this step-by-step and arrive at the right answer.
CH
Cherri
11 months ago
Okay, this looks tricky. I'll need to really focus and think through each answer choice systematically. Identifying the one that doesn't accurately describe total float will be the key.
ER
Ernest
12 months ago
Hmm, this question is testing my knowledge of critical path and schedule analysis. I'll need to make sure I have a solid grasp of the key definitions and formulas.
SA
Salley
12 months ago
I think I know how to approach this one - I'll need to understand the concept of total float and how it's calculated, then carefully evaluate each of the answer choices.
JO
Joni
7 months ago
I think that's the tricky part to watch out for.
RY
Ryann
7 months ago
But can it really be negative?
LO
Louis
7 months ago
I believe total float is all about timing.
AR
Arlene
11 months ago
Right, it shows how much you can delay tasks.
IR
Irma
1 year ago
I’m pretty sure D is correct because it matches the formula we learned for calculating total float.
IV
Ivette
1 year ago
I practiced a similar question where we had to identify incorrect statements about float, and I feel like C might be tricky too.
JE
Jeff
1 year ago
I think option B sounds a bit off. I don't recall float being negative; it’s usually just a positive number or zero.
RO
Rosalyn
1 year ago
I remember that total float is usually about how much you can delay an activity without affecting the project end date.