Each of the following accurately describes total float in a schedule EXCEPT:
Total float measures the flexibility in an activity's timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project's overall completion date or the completion date of any of its successors.
Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.
Option C describes free float, not total float, and thus is incorrect.
Alexis
2 months agoPeter
3 months agoGennie
3 months agoGoldie
3 months agoMelynda
3 months agoMagnolia
3 months agoGlynda
3 months agoKanisha
4 months agoAvery
4 months agoCorinne
4 months agoKattie
4 months agoMatthew
4 months agoDenny
4 months agoElbert
5 months agoSilva
5 months agoLevi
5 months agoThersa
5 months agoAn
6 months agoCherri
6 months agoErnest
6 months agoSalley
6 months agoJoni
1 month agoRyann
2 months agoLouis
2 months agoArlene
5 months agoIrma
6 months agoIvette
7 months agoJeff
7 months agoRosalyn
7 months ago