New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

AACE International AACE-PSP Exam - Topic 4 Question 42 Discussion

Actual exam question for AACE International's AACE-PSP exam
Question #: 42
Topic #: 4
[All AACE-PSP Questions]

Each of the following accurately describes total float in a schedule EXCEPT:

Show Suggested Answer Hide Answer
Suggested Answer: C

Total float measures the flexibility in an activity's timing within a schedule. It is defined as the amount of time an activity can be delayed without affecting the project's overall completion date or the completion date of any of its successors.

Option A, B, and D accurately describe total float: it is calculated as the difference between early and late start/finish dates, can be positive or negative, and is associated with project completion.

Option C describes free float, not total float, and thus is incorrect.


Contribute your Thoughts:

0/2000 characters
Peter
3 days ago
I think D is straightforward. It’s all about early and late finishes.
upvoted 0 times
...
Gennie
8 days ago
Right! A, C, and D all sound correct to me.
upvoted 0 times
...
Goldie
13 days ago
Yes, B doesn't make sense. Float can't be negative.
upvoted 0 times
...
Melynda
18 days ago
I agree! I feel like B is the odd one out.
upvoted 0 times
...
Magnolia
23 days ago
D is correct; that’s how you calculate float!
upvoted 0 times
...
Glynda
28 days ago
C is misleading; it’s not just about other activities.
upvoted 0 times
...
Kanisha
1 month ago
Wait, can float really be negative? That sounds weird.
upvoted 0 times
...
Avery
1 month ago
I agree, A is spot on!
upvoted 0 times
...
Corinne
1 month ago
Option B is the funniest answer. Total float can be positive or negative, just like my mood during exams.
upvoted 0 times
...
Kattie
2 months ago
Option A is wrong. Total float is the amount of time an activity can be delayed without delaying the project completion.
upvoted 0 times
...
Matthew
2 months ago
Option C is the best description of total float. It's the amount of time an activity can be delayed without affecting other activities.
upvoted 0 times
...
Denny
2 months ago
Option D is the correct answer. Total float is computed by subtracting early finish from late finish or early start from late start.
upvoted 0 times
...
Elbert
2 months ago
Option B is correct. Total float can be positive or negative.
upvoted 0 times
...
Silva
2 months ago
Total float - that's a concept I struggled with a bit in class. I'll need to review my notes and make sure I fully understand it before attempting this.
upvoted 0 times
...
Levi
3 months ago
Total float is definitely the time an activity can be delayed without affecting the project.
upvoted 0 times
...
Thersa
3 months ago
I think the question is tricky. Total float can be confusing.
upvoted 0 times
...
An
3 months ago
This is a classic project management question. I'm pretty confident I can work through this step-by-step and arrive at the right answer.
upvoted 0 times
...
Cherri
3 months ago
Okay, this looks tricky. I'll need to really focus and think through each answer choice systematically. Identifying the one that doesn't accurately describe total float will be the key.
upvoted 0 times
...
Ernest
4 months ago
Hmm, this question is testing my knowledge of critical path and schedule analysis. I'll need to make sure I have a solid grasp of the key definitions and formulas.
upvoted 0 times
...
Salley
4 months ago
I think I know how to approach this one - I'll need to understand the concept of total float and how it's calculated, then carefully evaluate each of the answer choices.
upvoted 0 times
Arlene
3 months ago
Right, it shows how much you can delay tasks.
upvoted 0 times
...
...
Irma
4 months ago
I’m pretty sure D is correct because it matches the formula we learned for calculating total float.
upvoted 0 times
...
Ivette
4 months ago
I practiced a similar question where we had to identify incorrect statements about float, and I feel like C might be tricky too.
upvoted 0 times
...
Jeff
4 months ago
I think option B sounds a bit off. I don't recall float being negative; it’s usually just a positive number or zero.
upvoted 0 times
...
Rosalyn
5 months ago
I remember that total float is usually about how much you can delay an activity without affecting the project end date.
upvoted 0 times
...

Save Cancel